Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 29044
THIRD DIVISION Docket No. MW-28879
91-3-89-3-291
The Third Division consisted of the regular members and in
addition Referee Herbert L. Marx, Jr. when award was rendered.

(Brotherhood of Maintenance of Way Employes PARTIES TO DISPUTE:



STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:

(1) The Carrier violated the May 21, 1979 Memorandum of Understanding when it abolished the Pane 1987 (System File NEC-BMWE-SD-2139).

(2) As a consequence of the aforesaid violation, Panel Renewal System Gang employes J. Wright, D. Adams, S. Clore, L. Slavin, W. B. Allison, K. Koppel and M. Rodden shall each be allowed pay at their respective straight time rates for forty (40) hours per week beginning December 17, 1987 and continuing until the violat
FINDINGS:

The Third Division of the Adjustment Board upon the whole record and all the evidence, finds that:

The carrier or carriers and the employe or employes involved in this dispute are respectively carrier and employes within the meaning of the Railway Labor Act as approved June 21, 1934.

This Division of the Adjustment Board has jurisdiction over the dispute involved herein.



At the time this dispute arose, the Claimants were members of the Panel Renewal System ("PRS") Gang. This Gang was established for special purposes under an Agreement dated May 21, 1979, which reads in pertinent part as follows:




Form 1 Award No. 29044
Page 2 Docket No. MW-28879
91-3-89-3-291









































Form 1 Award No. 29044
Page 3 Docket No. MW-28879
91-3-89-3-291
A June 12, 1981 letter amendment to the Agreement stated in pertinent
part as follows:









The May 21, 1979 Agreement makes reference to Rule 90-A. This Rule provides that the Carrier "may establish one or more of the following track units not assigned fixed headquarters to work over the Southern District." The Panel Renewal System is listed as one of these units, and Rule 90-A provides detailed requirements as to the establishment and operation of such units.

Also relevant here, as argued by the Carrier, is Rule 23, which states in pertinent part:



On December 17, 1987, the Claimants' positions in the PRS unit were abolished. The Carrier contended that "all scheduled interlocking rehabilitation work for which ther the dispute here under review, with the Organization initiating a Claim on January 7, 1988.
Form 1 Award No. 29044
Page 4 Docket No. MW-28879
91-3-89-3-291

At a later time, on June 8, 1988, the Carrier advised the Organization that it had "now received suf this [PRS) unit," and this was made effective thereafter. Of course, this resumption of PRS work was not known at the time the Claim herein was initiated.

The Organization argues that the May 21, 1979 Agreement prohibits the Carrier from removing the Claimants from their PRS positions at the time it did so. The Organization points in particular to Paragraph 5, which states:



Stated in broad strokes, it is the Organization's position that the Carrier has simply evaded this requirement by abolishing the PRS positions, despite the contention that the'program was not "completed or terminated" as evidenced (after the fact) by the program's resumption six months later.

The Carrier contends that nothing in the May 21, 1979 Agreement or its amendments prohibits the action taken, given its general rights under Rule 23 to reduce forces or abolish positions. The Carrier maintains that the PRS program was, in fact, "completed" in December 1987. The Carrier further notes the permissive language of Rule 90-A, to which the Agreement refers, in its statement that the Carrier "may" establish a variety of units such as PRS, but is not required to do so.

As to "work force stabilization provisions" of the Agreement, the Carrier refers to the June 12, 1981 letter, quoted above, which leaves this open for future discussion.

The Board finds no Rule support for the Organization's assumption that the Carrier is required to continue the PRS.program in the absence of anticipated work to be performed.. The theory advanced by the Organization is that the cessation in December and resumption the following June was simply a ploy to avoid continuing the Claimants in their positions during the winter months. This, however, is speculative. There is no basis to dispute the Carrier's contention that, as of December 1987, PRS work was "completed."

The Board's conclusion is supported by the Board of Arbitration Award issued May 16, 1988, involving the same parties but a different special program. While the facts and circumstan under review here, the conclusions therein are applicable here.




Form 1 Award No. 29044
Page 5 Docket No. MW-28879
91-3-89-3-291
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division

Attest.


Dated at Chicago, Illinois, this 22nd day of November 1991.