Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 29076
THIRD DIVISION Docket No. MW-29554
91-3-90-3-501
The Third Division consisted of the regular members and in
addition Referee Elizabeth C. Wesman when award was rendered.
(Brotherhood of Maintenance of Way-Employes
PARTIES TO DISPUTE:
(Burlington Northern Railroad Company (former
( Fort Worth and Denver Railway Company)
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood
that:
(1) The dismissal of Welder Helper Van Nelson, III for alleged violation of Rules
'...
564, 570, 571 and 576 of Form 15001 ***' in connection
with his
'...
failure to report,for duty September 23, 1989
....'
was arbitrary, unwarranted, exceedingly harsh and in violation of the Agreement
(System File F-89-56/MWD 90-1-26 FWD).
(2) The Claimant shall be returned to service with seniority and all
other rights unimpaired and shall be compensated for wage loss suffered in
accordance with Rule 28."
FINDINGS:
The Third Division of the Adjustment Board, upon the whole record
and all the evidence, finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employes within the meaning of the
Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the
dispute involved herein.
Parties to said dispute waived right of appearance at hearing
thereon.
At the time of the incident at issue in this case, the Claimant was
employed as a welder helper, headquartered at Amarillo, Texas. His work week
was Monday-Friday with rest days of Saturday and Sunday.
At some time prior to September 23, 1989, a rail detector car had
traversed the main line track between Amarillo and Channing, Texas, and had
detected more than eighty weld defects in the rail. As a result, slow orders
were issued until the track could be repaired. By September 22, 1989, there
was still repair work required and work was scheduled for both Saturday and
Sunday. All available welding employees, including Claimant, were advised of
the weekend work requirement.
Form 1 Award No. 29076
Page 2 Docket No. MW-29554
91-3-90-3-501
It is clear from the on-property record that Claimant understood the
Roadmaster's instructions regarding the weekend work, but advised him that he
would not work on Saturday because that was his religious Sabbath. The Claimant was subsequently dis
1989, but was restored to service by the Carrier on December 11, 1989.
The dispute in this case arose because Claimant, an avowed Seventh
Day Adventist, refused to work on Saturday, September 23, 1989, on the basis
of his religious beliefs. In disputes of this nature the Board has made a
practice of following the guidance of the U.S. Supreme Court's decision in
TransWorld Airlines, Inc. v. Hardison. 432 U.S. 63 (1977); Second Division
Awards 8226, 8660, 10121, 10291, 10401, 10613, 10927, 11510; Third Division
Award 22370. On the record before us, there is no dispute that the Carrier
had accommodated Claimant's desire to be absent on his Sabbath in the past,
but that in this particular case, his services were needed, and no accommodation was reasonably poss
Claimant's action materially hampered Carrier's ongoing effort to
correct a serious track problem. Accordingly we see no reason to disturb
Carrier's assessment of discipline.
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest:
Nancy ever - Executive Secretary
Dated at Chicago, Illinois, this 19th day of December 1991.