Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 29090
THIRD DIVISION Docket No. MW-28885
92-3-89-3-286
The Third Division consisted of the regular members and in
addition Referee Herbert L. Marx, Jr. when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Union Pacific Railroad Company (former Missouri
( Pacific Railroad Company)
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when it assigned outside
forces (Auto Truck) to install hy-rail attachments in Truck Units 63579
and 63749 which were delivered to the Carrier on April 7, 1988 and April
14, 1988, respectively (Carrier's File 880311 MPR).
(2) The Carrier also violated Article IV of the May 17, 1968 National
Agreement when it did not give the General Chairman advance written notice of
its intention to contract said work.
(3) As a consequence of the violations referred to in Parts (1)
and/or (2) above, the Eastern District Work Equipment Mechanics listed below*
shall each be allowed pay at their respective straight time rates for an equal
proportionate share of the one hundred forty-eight (148) man-hours expended by
outside forces performing the work listed in Part (1) above.
D. L. Wharton H. S. Wells
D. E. Price R. A. Grooms
R.
L.
Smith J. P. Koenigsfeld
R. M. Ussery R. G. Holman"
R.
L.
Goodin
FINDINGS:
The Third Division of the Adjustment Board, upon the whole record
and all the evidence, finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employes within the meaning of the
Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the
dispute involved herein.
Parties to said dispute waived right of appearance at hearing
thereon.
m
Form 1 Award No. 29090
Page 2 Docket No. MW-28885
92-3-89-3-286
In April 1988, two trucks were delivered to Carrier work gangs. The
trucks were delivered with the Hy-rail attachments installed by an outside
firm.
There is no dispute that, on occasion, such units are delivered
without the Hy-rail attachments, and such are installed by Carrier forces.
As the Board views it, this is an instance in which the Carrier has
determined to purchase equipment rather than perform installation work on the
property. The applicable Scope Rule is clearly general in nature, so any
question of reservation of the particular work is not at issue.
Because of the Carrier's decision to purchase the completed product,
the question of applicability of Article IV, Contracting out, also does not
arise. Of relevance here is Third Division Award 28561, which states as
follows:
"In prior Ayards, this Board has drawn a
distinction between the purchase of material
finished to specifications and the purchase of
unfinished goods or component parts which require
additional work by covered employees . . . . In
(prior cases] the Board held the purchase of
finished goods did not constitute subcontracting.
In this case, the Carrier avers its contract
was with C.F.I. for the purchase of welded rail.
C.F.I., in turn, contracted with Holland to perform
the welding. The Carrier did not take delivery of
the rail until it had been welded. There is no
evidence In the record to suggest there was any
privity of contract between Holland and the
Carrier. We must conclude, therefore, that the
Carrier purchase finished products and did not
engage in contracting out. The Agreement was not
violated.
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest:
a cy J. -Executive Secretary
Dated at Chicago, Illinois, this 23rd day of January 1992.