Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 29109
THIRD DIVISION Docket No. MW-29286
92-3-90-3-183
The Third Division consisted of the regular members and in
addition Referee Charlotte Gold when award was rendered.
(CSX Transportation, Inc. (formerly The Seaboard Coast Line
( Railroad Company)
PARTIES TO DISPUTE:
(Brotherhood of Maintenance of Way Employes

STATEMENT OF CLAIM:

"(1) The Agreement was violated when beginning sometime in February 1989, Bulk Distribution Services, Inc. contracted with an outside party to reconstruct trackage at Howell Yard, Atlanta, Georgia without confering (sic) with the General Chairman. [Carrier's file 12 (898-541), Organization's file ATL/WAY-89-18].

(2) As a consequence of the aforesaid violation, K. J. Turner, John Rowland, Jr., R. M. Chaney, Jr., C. E. Clements, M. Alexander, Jr., C. Heard, D. W. Thompson, A. G. Hale, C. Daniels and G. E. Alexander be allowed an equal proportionate share of an unspecified number of man hours consumed by Midway Construction Company in performing work for Bulk Distribution Services, Inc."

FINDINGS:

The Third Division of the Adjustment Board upon the whole record and all the evidence, f_nds that:

The carrier or carriers and the employe or employes involved in this dispute are respectivel? carrier and employes within the meaning of the Railway Labor Act as approved June 21, 1934.

This Division of the Adjustment Board has jurisdiction over the dispute involved herein.



The Organization alleges that some time in February 1989, Carrier permitted an outside contractor, Midway Construction Company, to perform reconstruction and overall track maintenance and/or repair work at the Howell Yard in Atlanta, Georgia. Work was done on the runaround track, depot 1, 2, 3, and piggyback tracks 1 and 2. The Organization points out that the work of constructing, dismantling, maintaining, and/or repairing tracks on Carrier's right-of-way and/or property is reserved to Track Subdepartment employees under Rules 1, 3, 4, and 5 of the parties' Agreement. It notes that Carrier violated Rule 2 by its failure to notify the General Chairman and allow the "Chief Engineering Officer and the General Chairman [to]...confer and reach an understanding setting forth the conditions under which the work will be performed."
Form 1 Award No. 29109
Page 2 Docket No. MW-29286
92-3-90-3-183

Carrier counters that the work in question was done by Midway forces at the request of Bulk Distribution Services, Inc., a separate corporate entity that leased the prop Distribution contracted out the work at its own expense and for its own benefit; that Bulk Distribut that the Carrier cannot be found in violation of the Agreement when it does not have the right to control the work in question. In support of its position, the Carrier provided Distribution, dated February 15, 1988.





The Carrier's argument that it did not control the work would have been more persuasive had it introduced into the record a copy of the Track Lease cited in the above-referenced document. Without its inclusion, this Board has no way of knowing whether the Carrier retained or did not retain control of the track and right-of-way on the property.

We note that is Third Division Award 28819, a case involving the same issue and the same parties (including Bulk Distribution Centers, Inc.) at Howell Mill Yard, the Board concluded that:


Form 1 Award No. 29109
Page 3 Docket No. MW-29286
92-3-90-3-183

That case is not directly on point with the instant dispute in that the parties, at that time (in August 1987, a year prior to the signing of the current Land Lease) were operating under a short-term, interim license (pending formal lease negotia be responsible for all expenses in conjunction with the work in question (track removal, switch work, reconstruction, and overall maintenance):



As noted previously, this Board has no way of knowing if these terms were ultimately incorporated into a formal Track Lease.

Given Carrier's affirmative responsibility to provide support for its contention that it did zot have the right to control the work in question (and its failure to do so), this claim must be sustained. Given that Claimants were fully employed at the time, no compensation will be awarded.








Attest:
      4n;ciy J. ;D Executive Secrety


Dated at Chicago, Illinois, this 28th day of February 1992.