Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 29120
THIRD DIVISION Docket No. MW-29207
92-3-90-3-76
The Thid Division consisted of the regular members and in
addition Referee John C. Fletcher when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(;;nion Pacific Railroad Company (former Missouri
( Pacific Railroad Company)
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:
(1) The claim* as presented by Second Vice Chairman B. R. Palmer on
October 8, 1988 to Manager of Program Services J. J. Stoner shall be allowed
as presented because said claim was not disallowed by Mr. Stoner in accordance
with Rule 12, Section =(a) (Carrier's File 890053 MPR).
(2) As a consequence of the aforesaid violation, Messrs. D. J. Steck,
S. P. Wood, M. A. Bucho1z, J. R. Smith, D. E. Kottwitz, R. M. Wachter, and W.
E. Brownlow shall each be paid forty-seven dollars and twenty-six cents
($47.26).
*The initial letter of claim will be reproduced
within our _nitial submission."
FINDINGS:
The Third Division of the Adjustment Board, upon the whole record
and all the evidence, finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employes within the meaning of the
Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the
dispute involved herein.
Parties to said dispute waived right of appearance at hearing
thereon.
On October 8, 1988, a Claim was filed with Carrier's Manager Program
Services seeking mileage payments on behalf of seven Machine Operators while
working in the vicinity of Jefferson City between August 5 and 8, 1988, which
had been submitted to :heir Supervisor on August 30, 1988, and were not approved by him. Carrier did
Under the terms of the Time Limits Rule of the Agreement, the Claim
must be allowed as presented without consideration of the merits of the matter.
Form 1 Award No. 29120
Page 2 Docket No. MW-29207
92-3-90-3-76
A W A R D
Claim sustained.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest:
ancy J. De Executive Secretary
Dated at Chicago, Illinois, this 28th day of February 1992.