Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 29185
THIRD DIVISION Docket No. MW-28886
92-3-89-3-281
The Third Division consisted of the regular members and in
addition Referee Herbert L. Marx, Jr. when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Union Pacific Railroad Company
(former Missouri Pacific Railroad Company)
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when it assigned outside
forces (Osmose Construction) to pour concrete, install anchors and apply epoxy
grout under the billit and rail plates in the East Scale approach beginning
June 6, 1986 (Carrier's File 860133).
(2) The Carrier also violated Article IV of the May 17, 1968
National Agreement when, it did not give the General Chairman advance written
notice of its intention to contract said work.
(3) As a consequence of the violations referred to in Parts (1)
and/or (2) above, B68 FDreman L. Edgar, Assistant Foreman L. Atkinson and
Carpenters R. Karr, R. 'jnes, C. Littleton, J. Miles, B. Miller and B. Seager
shall each be allowed pav at their respective straight time and overtime rates
for all hours expended by the contractor performing the work identified in
Part (1) above beginnin, lone 6, 1986 and continuing until the violation is
corrected."
FINDINGS:
The Third Division of the Adjustment Board upon the whole record
and all the evidence, finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employes within the meaning of the
Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the
dispute involved herein.
Parties to sa_u dispute waived right of appearance at hearing thereon.
In June 1986 t'-.e Carrier contracted with an outside firm to perform
concrete work in the Kansas City Terminal. This work consisted of pouring
concrete and installing anchors in the East Scale approach and applying epoxy
grout. The Organization argues that the Carrier failed to give appropriate
advance notice of the work and that the work was of a nature which should have
been performed by maintenance of way forces.
Form 1 Award No. 29185
Page 2 Docket No. MW-28886
92-3-89-3-281
The Carrier offers evidence of contracting out work similar to that
here under review in 251 separate instances for a period of almost 20 years
prior to the filing of the Claim. This appears to the Board to be a sufficient basis for a determina
With this finding, the Board does not examine other arguments raised
by the Carrier as to the effect of the "general" Scope Rule and the degree to
which maintenance of way forces have or have not performed such work.
The Board is fully aware and in support of previous Awards finding
the Carrier at fault in failing to provide the requisite advance notice, even
where examination of the merits leads to the conclusion that maintenance of
way forces were not improperly denied opportunity to perform the work. In
this instance, however, there is a largely undisputed account of contracting
out this particular type of construction work over many years. This is sufficient to warrant a denia
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest:
ncy J er·- Executive Secretary
Dated at Chicago, Illinois, this 3rd day of April 1992.