Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 29221
THIRD DIVISION Docket No. MW-28509
92-3-88-3-318
The Third Division consisted of the regular members and in
addition Referee Gil Vernon when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(CS% Transportation, Inc. (former Seaboard System Railroad)
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when, without an understanding having been reached betwee
the General Chairman setting forth the conditions under which the work will be
performed as required by Rule 2, it assigned outside forces to perform Maintenance of Way work at th
beginning May 4, 1987 [System File TOFC-87-69/12(87-917)).
(2) As a consequence of the violation referred to in Part (1)
above Messrs. D. Gaymon, R. Drew, J. Bath, E. Powlesland, L. B. Brownlee, I.
Coakley, N. Bryant, R. Teder, D. L. Timmons, R. H. Byrd, J. W. Adams, B. R.
Bethea, W. Harris and `!. McKissick shall each be allowed pay at their respective rates for an equal
expended by outside forces in the performance of the work referred to in Part
(1) above."
FINDINGS:
The Third Division of the Adjustment Board upon the whole record
and all the evidence, ands that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employes within the meaning of the
Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the
dispute involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
The claim before the Board involves the interpetation and application
of Rule 2 (Contracting) of the Parties' Agreement. It reads as follows:
Form 1 Award No. 29221
Page 2 Docket No. MW-28509
92-3-88-3-318
"RULE
2
This Agreement requires that all maintenance work
in the Maintenance of Way and Structures Department
is to be performed by employees subject to this
Agreement except it is recognized that, in specific
instances, certain work that is to be performed
requires special skills not possessed by the employees and the use of special equipment not owned by
or available to the Carrier. In such instances, the
Chief Engineering Officer and the General Chairman
will confer and reach an understanding setting forth
the conditions under which the work will be performed.
It is further understood and agreed that although
it is not the intention of the company to contract
construction work in the Maintenance of Way and
Structures Department when company forces and equipment are adequate and available, it is recognized
that, under certain circumstances, contracting of
such work may be necessary. In such instances, the
Chief Engineering Officer and the General Chairman
will confer and reach an understanding setting forth
the conditions under which the work will be performed. In such instances, consideration will be
given by the Chief Engineering Officer and the
General Chairman to performing by contract the
grading, drainage and certain other Structures
Department work by magnitude or requiring special
skills not possessed by the employees, and the use
of special equipment not owned by or available to
the Carrier and to performing track work and other
Structures Department work with company forces."
It is the position of the Organization that the Carrier contracted
for the work in question without consulting the General Chairman as required
by the Agreement. It also contends that the Carrier's defenses for violating
the Agreement are without merit. First, the claim was submitted within 60
days of when the contracting started, which is the key date, in its opinion.
Second, it believes it improper for Carrier to rely on efficiency and/or
economy in its attempt to justify its violation of the Agreement. In this
regard, it is suggested that lack of managerial foresight cannot be an excuse
for not having Carrier forces available. The work of the Carrier's forces or
the work of the ccntractor could have been rescheduled. Thus, additionally
it contends no loss of work opportunity need be proven to sustain the claim.
Form 1 Award No. 29221
Page 3 Docket No. MN-28509
92-3-88-3-318
The Carrier contends at the outset that the claim is time barred.
It notes that the notice was dated April 20, 1987, and the claim was not filed
until July 2, 1987, beyond the 60-day time limit. It also maintains that the
General Chairman tried to avoid the conference required by the Agreement. It
also maintains that Rule 2 is not an absolute prohibition against contracting.
The General Chairman cannot convert his refusal tactics and refusal to consent
to the contracting into a violation of the Agreement on the Carrier's part.
Contracting is permitted under certain circumstances. The facts of this situation fit the identified
Several issues need to be addressed. First, there is no merit to the
Carrier's time limit argument. The Organization is absolutely correct that
the mere issuance of a notice is not sufficient to toll the time limits in
circumstances such as these. Second, there is no basis for the Organization's
complaint that the contract was let prior to the conference. The level of
mutual animosity between the Parties makes it difficult in this case to determine, to use a figure o
Regarding the merits of the Carrier's decision to contract the work
in question the Board finds its decision considered and within the permissible
parameters for contracting encompassed in Rule 2. In this connection, there
are several significant factors which, in combination with each other, justify
the contracting under the unique circumstances of this case. They include (1)
the fact no employees were on furlough in the seniority district, (2) the fact
all active employees and equipment were committed elsewhere, and (3) a certain
degree of urgency to the project. The Organization did argue that the Carrier
could have reorganized, reallocated, and rescheduled the work to make the
Carrier forces available. The Carrier responded with validity that the project was driven by shipper
loss of business. We also note that the sheer magnitude of the project (3-4
months) speaks to the practicalities of delaying other projects in order to
utilize Carrier forces.
In summary, the Board cannot find that the Agreement was violated
under the circumstances presented by this record.
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest:
~/C~/
Nancy J. er - Executive Secretary
Dated at Chicago, Illinois, this 7th day of May 1992.