Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 29299
THIRD DIVISION Docket No. MW-29290
92-3-90-3-188
The Third Division consisted of the regular members and in
addition Re=eree Charlotte Gold when award was rendered.
~SX Transportation, Inc. (formerly The Seaboard Coast
Line Railroad Company)
PARTIES TO DISPUTE:
~3rotherhood of Maintenance of Way Employes

STATEMENT OF CLAIM:

"(1) The A3reement was violated when the Carrier, without conferring with the General Chairman, assigned work of pouring concrete slabs at Uceta Yard, Tampa, Florida :o an outside party (Ray Davies Construction Company) during a period May :5, 1989 through mid June 1989. [Carrier's file 12 (89-733), Organization's file CARP-89-33].

(2) As a consequence of the aforesaid violation, Carpenter Foreman
C. L. Roberts, Carpenters A. Oladell, B. J. Moore, Carpenter Helpers D. L.
McCarty, G. L. Farquarharson, and E. L. Stanaland shall each be allowed 120
hours pay each at their respective straight time rates."

FINDINGS:

The Third Division of the Adjustment Board upon the whole record and all the evidence, finds that:

The carrier or carriers and the employe or employes involved in this dispute are respectively carrier and employes within the meaning of the Railway Labor Act as approved June 21, 1934.

This Division of the Adjustment Board has jurisdiction over the dispute involved herein.



At issue in this dispute is the contracting out of concrete work at the Uceta Yard in Tampa, Florida, 'between May 15 and mid-June, 1989. The job of forming up and pouring a concrete slab (6" thick; 230' x 34') was given to the Ray Davies Construction Company. The Organization alleges that the work performed by six contractor employees rightfully belongs to Maintenance of Way Bridge and Building Subdepartment employees and the subcontracting here was entered into in violation of Rule 2, Contracting, of the Agreement. The Organization seeks 120 man hours for each of the named Claimants.
Form 1 Award No. 29299
Page 2 Docket No. MW-29290
92-3-90-3-188



"RULE 2

CONTRACTING


































the Maintenance of Way and Structures Department" is to be performed by employ
ees subject to the Agreement. The record of this case reveals that Mainten
ance of Way and Structure Department personnel have not been exclusively re
sponsible for concrete work at the Yard. Carrier contended that employees
covered by the Carmen, Sheet Metal Workers, and Electrician's Agreements had
also built forms and poured cement. Third Division Awards 26209, 26551 and
27169, involving the same parties at the same location, support that conten
tion. The real question thus becomes whether Carrier must ensure that the
disputed work be performed by Department personnel and only contract it out
under limited circumstances where (a) the Scope Rule is general in nature and
(b) the work is not specifically and exclusively reserved to Maintenance of
Way and Structures Department employees.
Form 1 Award No. 29299
Page 3 Docket No. MW-29290
92-3-90-3-188

Although the )rganization does not have the burden of proving that it has performed certain work exclusively in cases involving outside contractors (that is, vis-a-vis absence of a work and position Scope Rule, and where the evidence indicates that by custom, history, and practice, the work has been performed by a wide variety of crafts, t.^.:s is not possible to do.

Because of :.-e Organization's failure to carry its burden in this case, this claim must Se denied.








Attest:
        Nancy J. ~Ef - Executive Secretary


Dated at Chicago, Ll_:nois, this 24th day of July 1992.