Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 29308
THIRD DIVISION Docket No. MW-28301
92-3-87-3-863
The Third Division consisted of the regular members and in
addition Referee Elliott H. Goldstein when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Union Pacific Railroad Company
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:
(1) The Agreement was violated when outside forces were assigned to
perform grading, trenching, dirt removal, backfilling and leveling work in the
vicinity of Mile Post 903 at the Altamont/Aspen Tunnels on the Wyoming Division beginning September
(2) The Agreement was further violated when the Carrier did not
afford the General --hairman a meeting to discuss the work referred to in Part
(1) as contemplated by Rule 52(a).
(3) As a consequence of the violations referred to in Parts (1)
and/or (2) above, furloughed Group 19 Roadway Equipment Operators D. L.
Squibb, L. E. Easton, J. F. Gerrard, J. R. Gillen, E. H. Wold, C. D. Steuben
and R. L. Goettshe shall each be allowed pay at the Class A Roadway Equipment
Operator's straight time rate for an equal proportionate share of the manhours expended by tae outsi
from November 18, 1986 and continuing through December 19, 1986."
FINDINGS:
The Third Division of the Adjustment Board upon the whole record
and all the evidence, finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employes within the meaning of the
Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the
dispute involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
This dispute concerns the Carrier's assignment to an outside concern
of certain roadbed stabilization work near Mile Post 903 east of Evanston,
Wyoming, in September 1986. On August 28, 1986, Carrier provided the General
Chairman with a notice of intent to contract out the work, stating that it
Form 1 Award No. 29308
Page 2 Docket No. MW-28301
92-3-87-3-863
...
has customarily been performed in this fashion pursuant to Rule 52(d)."
On September 5, 1986, the General Chairman wrote the Carrier objecting to the
Carrier plans to contract out the work and requested ~ conference to discuss
the matter. Further correspondence by the Organization requesting a conference proved unavailing and
15, 1986, and ending December 19, 1986.
During the handling of this dispute on the property, the Organization
asserted that the contracted work is of a character that is contractually reserved to, and has custo
craft; instead, it contended on the property that its actions were justified
on the grounds that the work required special equipment and supervisory skills
and the past practice supported its action. In its Submission before this
Board, Carrier raised a number of additional arguments for the first time. As
we have reiterated on numerous occasions, however, we are authorized to consider only the arguments
handling of the dispute on the property. Newly presented arguments must be
deemed waived.
These arguments which have been considered as properly presented by
the Carrier are in the nature of an affirmative defense. Rule 52 permits the
Carrier to contract out work if certain exceptional circumstances are present.
These include situations where special skills are required that the employees
do not possess or special equipment must be used that the Carrier does not
own; unavailability of material due to a supplier maintaining exclusivity in
installing the material, and an emergency. The burden of establishing these
exceptions to the general prohibition against subcontracting is on the Carrier, and we do not believ
evidence was offered co support its assertions. We will sustain the claim on
that basis. It shouid be noted that in so doing, we make no finding that
Carrier violated the Agreement by failing to hold a conference on the matter
pursuant to the Organization's requests. Based on our review of the correspondence, it appears that
unable to ascertain from the record why no conference took place.
The remaining issue concerns the remedy for the violation. It is the
intent of this Award to make Claimants, furloughed at the time of the dispute,
whole and they are to be compensated for the amount of time that the outside
forces worked, such time to be determined by the parties, who are directed to
consult the work records to determine the appropriate number of hours.
A W A R D
Claim sustained in accordance with the Findings.
Form 1 Award No. 29308
Page 3 Docket No. MW-28301
92-3-87-3-863
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
ATtest:
ncy J. D Executive Secretary
Dated at Chicago, Illinois, this 24th day of July 1992.