Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 29309
THIRD DIVISION Docket No. MW-28403
92-3-88-3-190
The Third Division consisted of the regular members and in
addition Referee Elliott H. Goldstein when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Union Pacific Railroad Company
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when it assigned outside
forces to perform the work of hauling material, installing grade, installing
ballast, removing asphalt, preparing track surfaces and grading work on the
intermodal facility at Los Angeles, California beginning December 9, 1986 and
continuing through April 24, 1987 (System File M-565/870501).
(2) The Agreement was further violated when the Carrier did not give
the General Chairman prior written notification of its plan to assign said
work to outside forces.
(3) As a consequence of the violations referred to in Parts (1)
and/or (2) above, System Roadway Equipment Subdepartment Operators R. S.
Hutchison, C. A. Hintz, D. L. Weber, E. L. Ramsy, S. D. Kleider, J. H. Scott,
J. L. Sherman, D. D. Dickinson and G. G. Pischel shall each be allowed eight
hundred twenty-two (822) hours of pay at their respective rates."
FINDINGS:
The Third Division of the Adjustment Board upon the whole record
and all the evidence, finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employes within the meaning of the
Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the
dispute involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
On or about December 9, 1986, and continuing through April 24, 1987,
Carrier assigned outside forces to perform what the Organization insists is
Roadway Equipment operator work, _i.e., hauling material, installing grade,
installing ballast, removing asphalt, preparing track surfaces and grading
work at the intermodal facility in Los Angeles, California. The Organization
Form 1 Award No. 29309
Page 2 Docket No. !iW-28403
92-3-88-3-190
asserts that the contracted out work is encompassed within the scope of the
Agreement and has been performed by its members as a matter of historical
practice. It also asserts lack of notice. Carrier contends that: (1) It did
furnish the Organization with the requisite notice of intent to subcontract;
(2) Claimants did. not possess all the skills required to complete the project
and Carrier should not be forced to "piecemeal" the work; (3) Claimants had
not done this type of work on an exclusive basis in the past, in fact, similar
work has been contracted out on numerous occasions; (4) the disputed work does
not fall within the scope of the Agreement.
As a preliminary point, this Board notes that certain arguments were
not exchanged on the property as required by long established precedent. The
only evidence and arguments that the Board can consider are those which have
been exchanged between the parties on the property.
Our reading of the record also shows that while there were instances
cited by the Organization where the work at issue was performed by employees
in the past, Carrier provided equally probative evidence that work of the kind
in dispute here has been contracted out frequently over a number of years. We
note, too, that the Organization in correspondence with Carrier during the
handling of this case on the property, acknowledged that such work had previously been contracted ou
the Organization has failed to meet its burden of establishing entitlement to
the work as a matter of past practice.
As to the notice issue, the record shows that the Organization raised
the question in its April 18, 1987 Claim and in its June S, 1987, notice of
appeal. On July 27, 1987, Carrier responded in pertinent part:
"You have based the major portion of this claim on
your contention that you were not provided advance
notice of the Carrier's intent to contract this project. It has recently become evident that your
Organization has lost several of your files dealing
with contracting, either that or you are attempting a
new ploy by pleading ignorance of any advance notice
when in fact you are in possession of one. My file
indicates that you were furnished notice of this
project in my letter of November 21, 1986. If you
are unable to locate this notice, please advise, and
I will arrange to furnish you with a copy of this
notice.
Form 1 Award
No. 29309
Page
3
Docket
No. MW-28403
92-3-88-3-190
There is no indication in the subsequent correspondence between the
parties on the property that the Organization requested a copy of the notice.
The only reference by the Organization to the notice issue following Carrier's
July 27, 1987
letter is the following response contained in a letter dated
April
29, 1988,
from the General Chairman:
°I also pointed out to you that I found it highly
unusual for the Carrier to serve notice of its intent
to solicit bids for contracting work which the Carrier contends is not Scope covered or work not cus
to the exclusion of all others. In response you
indicate one should not assume that such notices are
necessarily an indication on the Carrier's part that
work is or is not scope-covered. However, you somewhat contradict yourself by indicating the Carrier
has in tie past and will in the future continue to
serve notice of both scope-covered work and work
'which reasonably could perhaps be perceived as
falling at least within the peripheral area of
scope-covered work.' In support of your position
you offered a quote from a nontypical Award
(21287).
Again, as stated previously, I cannot agree with your
position. It must be remembered Rule
52
requires
prior written notice of intent to contract only if
work is Scope covered. The Carrier's notices have
not been informational in nature only and represent
document evidence of the Carrier's recognition that
the work in dispute in each case is encompassed within the Scope of one Agreement. Below are some pe
(2)
of the obviously more
well-reasoned awards addressing this issue."
Under these unique circumstances, where there is no evidence that the
Organization heeded Carrier's offer to supply another copy of the notice, and
where the Organization at least tacitly suggested at a later date that it had
received notice, but was challenging the meaning to be attached to it, vis a
vis the Scope Rule, we cannot find that there is sufficient evidence that
Carrier failed to adhere to the notice requirements of the contract.
In light of the foregoing findings, we need not, and therefore will
not, address the additional defenses raised by the Carrier in connection with
Rule
52.
We will rule to deny the Claim in its entirety.
A W A R D
Claim denied.
Form 1 Award No. 29309
Page 4 Docket No. MW-28403
92-3-88-3-190
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest:
ncy J. - Executive Secretary
Dated at Chicago, Illinois, this 24th day of July 1992.