(Brotherhood of Maintenance (of Way Employes PARTIES TO DISPUTE: (Consolidated Rail Corporation

STATEMENT OF CLAIM:









FINDINGS:

The Third Division of the Adjustment Board upon the whole record and all the evidence, finds that:

The carrier or carriers and the employe or employes involved in this dispute are respectively carrier and employes within the meaning of the Railway Labor Act as approved June 21, 1934.

This Division of the Adjustment Board has jurisdiction over the dispute involved herein.
Form 1 Award No. 29507
Page 2 Docket No. MW-29915
93-3-91-3-283

Parties to said dispute waived right of appearance at hearing thereon.


The Carrier advertised a Class 1 Machine operator position on Bulletin #26 on May 22, 1989. The Bulletin specified that applications would be accepted in the office of the Division Engineer until 4:30 P.M. on Monday, May 29, 1989. The deadline was extended to May 30 since May 29 was a holiday.


A Repairman, with a seniority date of June 2, 1977, filed a timely bid and was awarded the position on May 31, 1989. Claimant, with a seniority date of September 27, 1974, mailed a bid to the Division Engineer's office on May 26. The record shows, however, that the bid was not received by that office until May 31, one day beyond the extended filing date. Given these facts and circumstances, and under well-established precedents of the Board, we are compelled to deny the claim.







Attest:


Dated at Chicago, Illinois, this 3rd day of February 1993.