NATIONAL RAILROAD ADJUSTMENT BOARD
Form 1 THIRD DIVISION Award No. 29558
Docket No. MW-28989
93-3-89-3-411
The Third Division consisted of the regular members and in
addition Referee Herbert L. Marx, Jr. when award was rendered.
(Brotherhood of Maintenance
(of Way Employes
PARTIES TO DISPUTE:
(Consolidated Rail Corporation
STATEMENT OF CLAIM:
"Claim of the System Committee of the Brotherhood that:
(1) The Agreement was violated when the carrier assigned
an outside contractor (Railroad Construction Company) to
unload ties along the right-of-way on the Harrisburg
Division beginning April 18, 1988 (System Docket MW-14).
(2) The Carrier also violated the Agreement when it did
not give the General Chairman advance written notice of
its intention to contract out said work.
(3) As a consequence of the violations referred to in
Parts (1) and/or (2) above, Machine Operator R. Snyder
shall be allowed pay for eight (8) hours each work day
beginning April 18, 1988 and continuing for as long as
the Railroad Construction Company unloaded ties on the
Harrisburg Division."
FINDINGS:
The Third Division of the Adjustment Board upon the whole
record and all the evidence, finds that:
The carrier or carriers and the employe or employes involved
in this dispute are respectively carrier and employe within the
meaning of the Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over
the dispute involved herein.
Parties to said dispute waived right of appearance at hearing
thereon.
Form 1 Award No. 29558
Page 2 Docket No. MW-28989
93-3-89-3-411
This dispute concerns the Carrier's contracting of the
unloading of railroad ties from gondola cars by use of the
contractor's equipment, which is described by the Carrier as a
"specially constructed backhoe...mounted on the gondola car."
No advance notice of the action was provided to the General
Chairman. The Scope Rule requires such notice where the Carrier
plans to "contract out work within the scope of the Agreement."
In this instance, the Carrier relies on long-established
practice of contracting out this particular work. There is no
clear prohibition to the Carrier's use of the special equipment,
particularly in view of past practice in doing so. The Carrier
also asserts that the Claimant, who was otherwise fully employed at
the time, was not qualified to operate such special equipment.
Given these circumstances, the failure to provide advance notice is
not sufficient to warrant sustaining the Claim.
Beyond and apart from the question of notice, the Organization
has not established a clear Rule violation in these particular
circumstances.
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest:
ancy J. er - Executive Secretary
Dated at Chicago, Illinois, this 9th day of March 1993.