NATIONAL RAILROAD ADJUSTMENT BOARD
Form 1 THIRD DIVISION Award No. 29595
Docket No. MW-28829
93-3-89-3-230
The Third Division consisted of the regular members and in
addition Referee Gilbert Vernon when award was rendered.
(Brotherhood of Maintenance
(of Way Employes
PARTIES TO DISPUTE'
(Duluth, Missabe and Iron Range
(Railway Company
STATEMENT OF CLAIM'
"Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when it assigned
IBEW Electricians T. Scott and F. Johnson instead of B&B
Mechanics to dismantle and rebuild the manual lever
operating mechanism on a door actuator on December 10 and
11, 1987 (Claim No. 3-88).
(2) As a consequence of the aforesaid violation, B&B
Mechanics G. M. Sjoguist and S. Applewick shall each be
allowed nine (9) hours of pay at their straight time
rates."
FINDINGS:
The Third Division of the Adjustment Board, upon the whole
record and all the evidence, finds that:
The carrier or carriers and the employe or employes involved
in this dispute are respectively carrier and employe within the
meaning of the Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over
the dispute involved herein.
Parties to said dispute waived right of appearance at hearing
thereon.
As Third Party in Interest, the IBEW was advised of the
pendency of this dispute and it did file a Submission with this
Board.
Form 1 Award No. 29595
Page 2 Docket No. MW-28829
93-3-89-3-230
It is the conclusion of the Board that the claim cannot be
sustained. The organization has not demonstrated that the work in
question is reserved to them by specific agreement language or by
history, custom or practice. The past practice relied on by the
Organization relates to a different technology. The evidence
suggests that repairs of the particular type of actuator involved
in this case had been performed by electricians after the actuator
has been removed from the gate by the B&B.
In view of the foregoing, the claim is denied.
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest:
Nancy J er.- Executive Secretary
Dated at Chicago, Illinois, this 9th day of March 1993.