NATIONAL RAILROAD ADJUSTMENT BOARD
Form 1 THIRD DIVISION Award No. 29644
Docket No. MW-28103
93-3-87-3-680
The Third Division consisted of the regular members and in
addition Referee Edwin H. Benn when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Duluth, Winnipeg & Pacific Railway Company
STATEMENT OF CLAIM:
"Claim of the System Committee of the Brotherhood
that:
(1) The Carrier violated the Agreement when it
assigned outside forces to install culverts
and reroute Flint Creek beginning September
22, 1986 (System File G. 106-N-86(S)/#208).
(2) The Carrier violated Rule 55 when it did not
give the General Chairman advance written
notice of its intention to contract said
(3) As a consequence of the aforesaid violation
Group I Machine Operator B. Netzel shall be
compensated for all straight time and overtime wage loss suffered beginning September
22, 1986 and continuing until such time as
the violation is corrected."
FINDINGS:
The Third Division of the Adjustment Board, upon the whole
record and all the evidence, finds that:
The carrier or carriers and the employe or employes involved
in this dispute are respectively carrier and employe within the
meaning of the Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over
the dispute involved herein.
Parties to said dispute waived right of appearance at hearing
thereon.
Claimant is a Group I Machine Operator in the Carriers B & B
Department. At the time this dispute arose, Claimant was furloughed. The on-property handling disclo
diameter culverts at MP 102.7 for the purposes of rerouting Flint
Form 1 Award No. 29644
Page 2 Docket No. MW-28103
93-3-87-3-680
Creek. The contractor utilized three large backhoes (ranging in
size from 1 to 2-2/3 cubic yard buckets) along with a D-6 dozer.
That type of equipment is not owned by the carrier. The Carrier
asserts that it is unable to rent that type of equipment, without
operators and even if its employes were qualified to operate that
type of equipment, the contractor would not have allowed them to do
so.
No notice was given by the Carrier to the Organization of its
intent to contract out this particular work.
Rule 55 states, in pertinent part:
"RULE 55 - CONTRACTING OUT
In the event a carrier plans to contract out work within the
scope of the applicable schedule agreement, the carrier shall
notify the General Chairman of the organization involved in
writing as far in advance of the date of the contracting
transaction as it is practicable and in any event not less
than 15 days prior thereto."
It is undisputed that the Carrier did not give the
Organization notice of its plans to contract out this work. The
type of equipment utilized and the work at issue clearly fell
"within the scope of the applicable schedule agreement" as
equipment utilized by and work performed by Group I Machine
Operators. Irrespective of the Carrier's contentions that it could
contract out the work under these given circumstances because it
did not own this equipment or because of the alleged lack of
qualifications of Claimant, nevertheless, before that issue can be
addressed, Rule 55 imposes a threshold obligation upon the Carrier
to give the organization advance notice of its intent to contract
out the work where the work falls within the scope of the
agreement. Because the Carrier did not give such notice in this
case, Rule 55 was not followed.
From the record, there are no apparent reasons evident why
full remedial relief should not be afforded. The claim will,
therefore, be sustained as presented but limited to the particular
project complained of.
Form 1 Award N. 29644
Page 3 Docket No. MW-28103
93-3-87-3-680
A W A R D
Claim sustained.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest:
Z',ee
~~
ancy ever, Secretary to the Board
Dated at Chicago, Illinois, this 7th day of June, 1993.