NATIONAL RAILROAD ADJUSTMENT BOARD
Form 1 THIRD DIVISION Award No. 29722
Docket No. MW-29239
93-3-90-3-114
The Third Division consisted of the regular members and in
addition Referee Herbert L. Marx, Jr. when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Duluth, Missabe and Iron Range Railway
(Company
STATEMENT OF CLAIM: "Claim of the System Committee of the
Brotherhood that:
(1) The Agreement was violated when the
Carrier assigned outside forces to remove
and replace concrete side walks and curbs
at the Duluth Ore Docks and Storage
Facility beginning August 24, 1988 (Claim
No. 28-88).
(2) The Carrier also violated Supplement No.
3 when it failed to timely and properly
notify and confer with the General
Chairman concerning said contracting
transaction.
(3) As a consequence of the violations
referred to in Parts (1) and/or (2)
above, the five (5) senior furloughed B&B
employes on the Missabe Division shall
each be allowed pay at their respective
straight time rates for an equal
proportionate share of the total number
of man-hours expended by the outside
contractor performing the work identified
in part (1) above."
FINDINGS:
The Third Division of the Adjustment Board, upon the whole
record and all the evidence, finds that:
The carrier or carriers and the employe or employes involved
in this dispute are respectively carrier and employe within the
meaning of the Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over
the dispute involved herein.
Form 1 Award No. 29722
Page 2 Docket No. MW-29239
93-3-90-3-114
Parties to said dispute waived right of appearance at hearing
thereon.
By letter dated August 10, 1988, the Carrier notified the
General Chairman in pertinent part as follows:
"This is to advise you that a contractor will
be on the property, possibly within a week, to
perform certain roadway and parking lot work
at Duluth Docks. Changes in traffic routing,,
and deterioration of existing surfaces will
removal of concrete gutter
removal of washed rock
removal of sidewalk sections
installation of new sidewalk
installation of new curb
landscaping
blacktopping
This work will be contracted due to the fact
that the equipment and skills necessary are
not available on the Carrier's property. This
notice is given without prejudice to the
Carrier's position that blacktopping and the
associated work is not work covered under the
Maintenance of Way rules."
The General Chairman responded to the Carrier on August 19,
1988, stating in part as follows:
"The B&B [forces] can perform the majority of
the work in question. We have the means and
the equipment and employees willing and able
and available to perform this work. In an
effort to come to a compromised agreement to
allow some of the work to be contracted [t]he
Organization would be willing to come to a
agreement and allow the black topping
....
If we cannot agree to some type of compromise,
[t]he Organization is again forced by the
Carrier to file a claim or claims for the
above work. We will be happy to meet with you
at your convenience."
Form 1 Award
No.
29722
Page 3 Docket
No.
MW-29239
93-3-90-3-114
The contracted work thereafter commenced and was completed on
September 9, 1988. On October 10, 1988, the Organization initated
a Claim in reference to all of the work. However, on March 31,
1989, the Organization modified the Claim to eliminate reference to
the blacktopping work (which was approximately three-quarters of
the project), leaving intact the claim as to sidewalks and curbing
in particular.
In further correspondence on December 14, 1989, the
Organization referred to the requirement in Supplement
No.
3 (c),
quoted below, that the Carrier give sufficient notice so that the
matter can be discussed in conference, pointing out that the notice
which was given was so close to the starting date of the work
(apparently already contracted) as to prohibit the possibility of
reaching any meaningful agreement as to the work.
At issue here is Supplement
No.
3, Contracting of Work, which
reads in pertinent part as follows:
(a) The Railway Company will make every
reasonable effort to perform all
maintenance work in the Maintenance of
Way and Structures Department with its
own forces.
(b) Consistent with the skills available in
the Bridge and Building Department and
the equipment owned by the Company, the
Railway Company will make every
reasonable effort to hold to a minimum
the amount of new construction work
contracted.
(c) Except in emergency cases where the need
for prompt action precludes following
such procedure, whenever work is to be
contracted, the Carrier shall so notify
the General Chairman in writing, describe
the work to be contracted, state the
reason or reasons therefor, and afford
the General Chairman the opportunity of
discussing the matter in conference with
Carrier representatives
...."
The Board finds that the organization's position has merit as
to the contracted work other than the blacktopping. The Board
concludes that the Carrier failed to meet its requirements under
Supplement No. 3 (a) and (b). A "reasonable effort" would reveal
that the sidewalk and curbing work could have been performed by
Form 1
Page 4
Award No. 29722
Docket No. MW-29239
93-3-90-3-114
Carrier employees who are qualified and who have done so in the
past.
The Carrier argues that it is not required to piecemeal a
construction project, given the inefficiencies which would
accompany such effort. This argument carries great weight in many
instances, but not in the circumstances here. Carrier forces did
perform some of the preliminary work for the project. In addition,
it turns out that the contractor itself subcontracted the sidewalk
and curbing work, so that it was clearly separate from the
blacktopping work.
The Carrier also notes that it currently had insufficient
supervision to cover projects such as involved here. This,
however, is hardly the type of justification for contracting
contemplated in Supplement No. 3. Finally, there is no showing
that the necessary skills or equipment were unavailable for the
limited portion of the work sought by the organization.
The Carrier may well argue that, throughout the initial stages
of the claim handling procedure, it was defending its position as
to the entire project, with the Organizations modification only
coming at a later point. While this is correct, it is reasonable
to assume that, if advance written notice had been given prior to
the apparent full commitment to outside forces, an accommodation
might well have been reached with the General Chairman as to a
portion of the work.
Supplement No. 3 is indeed limited in its coverage, as pointed
out in many other Awards. It is, however, meaningful, and it
cannot be relied on to cover any and all types of contracting.
A W A R D
Claim sustained.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Nancy J. er - Secretary to the Board
Dated at Chicago, Illinois, this 12th day of August 1993.