NATIONAL RAILROAD ADJUSTMENT BOARD
Form 1 THIRD DIVISION Award No. 29751
Docket No. MW-29958
93-3-91-3-350



(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:


STATEMENT OF CLAIM: "Claim of the System Committee of the

Brotherhood that:





FINDINGS:

The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:

The carrier or carriers and the employe or employes involved in this dispute are respectively carrier and employe within the meaning of the Railway Labor Act as approved June 21, 1934.
Form 1 Award No. 29751
Page 2 Docket No. MW-29958
93-3-91-3-350

This Division of the Adjustment Board has jurisdiction over the dispute involved herein.


Parties to said dispute waived right of appearance at hearing thereon.


After first serving notice on the organization of its intent to subcontract, the Carrier proceeded to utilize an outside contractor to perform cross tie and ballast work at two locations. The Organization contends that this work has been customarily and traditionally assigned to and performed by its members, and that the Carrier violated Article IV of the National Agreement when it contracted out the work.


Article IV of the National Agreement is pertinent to a resolution of this dispute, and reads as follows:






Form 1 Award No. 29751
Page 3 Docket No. MW-29958


The issue presented in this dispute has been addressed by the Board on numerous occasions. For example, in Third Division Award 29037, the Board concluded:


          "The Scope Rule is a general Rule and the onproperty record is conclusive that the work has not been "customarily" performed by employees. The letters submitted by B&B Painters do not refute the Carrier's evidence that it utilized outside forces for decades to perform work which included painting. The Organization's rebuttal on the property of the sixty-four year record, including the point that the Omaha headquarters was painted by outside contractors only three times in that period, is not on point. It is central to this dispute that proof has been presented by the Carrier that outside forces historically painted buildings, including the Headquarters Building. This probative evidence removes this work from that which the Carrier is restricted from contracting out and is required to give advance notice."


Numerous decisions of the Board have held that the Carrier has the right under Article IV to contract out work where advance notice is given and the Carrier has established a mixed past practice of contracting out work similar to that involved in the dispute. The record in this case demonstrates a mixed practice on this property with respect to the work in question. It has been performed by members subject to the Agreement in the past but has also been contracted out by the Carrier in the past. We thus conclude that the Carrier did not violate the Agreement when it contracted out the work.


                        A W A R D


      Claim denied.


                          NATIONAL RAILROAD ADJUSTMENT BOARD By Order of Third Division


                    v~


Attest: / ..Lc~r
Catherine Loughrin -J nterim secretary to the Board

Dated at Chicago, Illinois, this 20th day of September 1993.