NATIONAL RAILROAD ADJUSTMENT BOARD
Award No. 29917
Docket No. MW-30090
93-3-91-3-518
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(National Railroad Passenger Corporation
((Amtrak) - Northeast Corridor
STATEMENT OF CLAIM: As shown in Docket No. MW-30090 and not
repeated herein.
FINDINGS: The Third Division of the Adjustment Board finds:
That the dispute was certified to the Third Division
of the Adjustment Board ex parte by the petitioning party; and
Under date of October 27, 1993, the petitioning party
addressed a formal communication to the Interim Secretary of the
Third Division requesting withdrawal of this case from further
consideration by the Division which request is hereby granted.
A W A R D
Claim withdrawn.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest:
Catherine Loughrin - I rim Secretary to the Board
Dated at Chicago, Illinois this 9th day of November 1993.