NATIONAL RAILROAD ADJUSTMENT BOARD
Form 1 THIRD DIVISION Award No. 30035
Docket No. MW-29618
94-3-90-3-602
The Third Division consisted of the regular members and in
addition Referee Herbert L. Marx, Jr. when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Elgin, Joilet and Eastern Railway Company
STATEMENT OF CLAIM: "Claim of the System Committee of the
Brotherhood that:
(1) The Carrier violated the Agreement when it assigned
an outside contractor (Dyer Construction Company)
to perform Bridge and Building Department work of
replacing culvert No. 169 located just south of
111th Street in Normantown, Illinois on April 4 and
5, 1989 and the capping of the old culvert on April
6, 1989 (System File BJ-10-89/UM-26-89).
(2) As a consequence of the aforesaid violation, B&B
Carpenter Foreman 0. Salaiz, B&B Carpenters J.
Quirk and B. Ruzich and Crane Operators G. Haggerty
and J. Barnes shall each receive twenty (20) hours
of pay at their respective time and one-half rates
of pay."
FINDINGS:
The Third Division of the Adjustment Board, upon the whole
record and all the evidence, finds that:
The carrier or carriers and the employe or employes involved
in this dispute are respectively carrier and employe within the
meaning of the Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over
the dispute involved herein.
Parties to said dispute waived right of appearance at hearing
thereon.
By letter dated December 23, 1988, the Carrier wrote to the
General Chairman, stating:
"This is to notify that the Carrier intends to
contract out the below-listed work due to the
magnitude of the planned 1989 Construction
Form 1 Award No. 30035
Page 2 Docket No. MW-29618
94-3-90-3-602
Proi ect on the Joliet and Gary Divisions re
quiring all available employees to be assigned
to work in other areas:
BR-169 NORMANTOWN, ILLINOIS REPLACEMENT OF
EXISTING CULVERT"
Such notice was in accord with Article IV of the May 17, 1968
National Agreement (Rule 6(c)], which states in pertinent part as
follows:
"In the event a carrier plans to contract out
work within the scope of the applicable schedule agreement, the carrier shall notify the
General Chairman of the organization involved
in writing as far in advance of the date of
the contracting transaction as is practicable
and in any event not less than 15 days prior
thereto.
If the General Chairman, or his representative, requests a meeting to discuss matters
relating to the said contracting transaction,
the designated representative of the Carrier
shall promptly meet with him for that purpose.
Said carrier and organization representatives
shall make a good faith attempt to reach an
understanding concerning said contracting, but
if no understanding is reached the carrier may
nevertheless proceed with said contracting,
and the organization may file and progress
claims in connection therewith."
In response to a timely request from the General Chairman, a
meeting was set for January 18, 1989, but this meeting was postponed by the Carrier and not held unt
was determined that contract for the work had already been let on
January 10, 1989, prior to both the initial and later dates for the
conference.
The record shows substantial evidence that the work was
"within the scope of the applicable schedule agreement", even if
there is evidence that such work was not consistently performed by
Carrier forces. The fact that the contract was let prior to the
requested discussion represents a denial of the opportunity to
review the matter in "good faith", as required by Rule 6(c). On
this basis, the sustaining Award is required.
Form 1 Award No. 30035
Page 3 Docket No. MW-29618
94-3-90-3-602
As to remedy, the carrier points to Rule 58,
which
states that
"time claims shall be confined to the actual pecuniary loss."
Since the Claimants were fully employed, the Carrier argues that no
monetary remedy would be appropriate. The Board does not agree.
Assuming that a timely conference had occurred prior to letting of
the contract, additional work may have been available to the
claimants (or others similarly situated). Whether this work would
have been performed by such employees or by adding to the force
would be the Carrier's option, but "pecuniary loss" can be demonstrated. However, payment at the str
the claimed time and one-half rate, is appropriate.
A W A R D
Claim sustained in accordance with the Findings.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest:
~IC-, °^(
Catherine Loughrini Interim secretary to the Board
Dated at Chicago, Illinois, this 17th day of February 1994.