NATIONAL RAILROAD ADJUSTMENT BOARD
Form 1 THIRD DIVISION Award
No.
30180
Docket
No.
MW-29523
94-3-90-3-469
The Third Division consisted of the regular members and in
addition Referee Herbert L. Marx, Jr. when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Southern Pacific Transportation Company
((Eastern Lines)
STATEMENT OF CLAIM: "Claim of the System Committee of the
Brotherhood that:
1. The Agreement was violated when the Carrier
assigned outside forces to perform rail grinding
work between Mile Post 815.2 at Bolen, Texas and
Mile Post 736.9 at Sierra Blanca from July 31
through August 5, 1989 (System File MW-89-97/485
52-A SPE).
2. The Agreement was further violated when the carrier
failed to furnish the General Chairman with advance
written notice of its intention to contract out
said work as required by Article 36.
3. As a consequence of the violations in Parts (1)
and/or (2) above, Welding Foreman R.K. Lankford,
Machine Operators H. R. Cordero, F. Fuentes and
Machine Operator Helper E. Rodriguez shall each be
allowed forty (40) hours of pay at their respective
straight time rates and forty-one and one-half
(41.5) hours of pay at their respective time and
one-half rates."
FINDINGS:
The Third Division of the Adjustment Board, upon the whole
record and all the evidence, finds that:
.The carrier or carriers and the employe or employee involved
in this dispute are respectively carrier and employe within the
meaning of the Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over
the dispute involved herein.
Parties to said dispute waived right of appearance at hearing
thereon.
Form 1 Award No. 30180
Page 2 Docket No. MW-29523
94-3-90-3-469
At issue here is the Carrier's use of an outside contractor
(Loram) to perform rail grinding work. There is no dispute that
rail grinding work is performed by Maintenance of Way forces. The
record is equally clear, however, that outside forces have been
employed for rail grinding both prior to and concurrent with such
work being undertaken by Carrier forces.
In response to a Claim concerning the contracting of such
work, the Carrier stated in its April 6, 1990 letter to the
organization as follows:
"The Southern Pacific Transportation Company purchased
two 40-stone rail grinders from Fairmont Railway Motors
in the early 1980s to be used primarily to grind curves.
[These are grinders operated by Carrier Maintenance of
Way employees.] Prior to obtaining these grinders, all
rail grinding was performed by outside forces. These two
machines are presently combined to get better
productivity and are working on the Western Lines. When
the work there is completed, the combined machines will
be moved to Del Rio, Texas, to grind the curves in West
Texas.
Recent tests have shown that the life of tangent rail can
be prolonged with a consistent maintenance-based program
of rail grinding. In order for this Carrier to implement
such a program, it was necessary to obtain additional
grinding capacity. Staring in 1989, we began using Loram
Maintenance of Way, Inc. to perform additional rail
grinding on both the Western and Eastern Lines. The
grinding stones on the Loram equipment are hydraulically
adjusted and computer controlled. This type of equipment
is not owned by. any railroad in the United States. The
rail grinding being performed by Loram could not be done
by Carrier forces using our Fairmont equipment, as the
magnitude of the program far exceeds the capacity of our
equipment".
The Organization contends that, after the parties established
rail grinding agreements, the Carrier "abolished the positions on
its rail grinding train and ceased operation in 1989." This is at
variance with the Carrier's contention of continued rail grinding
operation by its forces. Whatever the facts may be, the question
before the Board is whether the Carrier violated the notice
provision of Article 36 and other Rules in its contracting specific
rail grinding work to Loram as indicated in the Statement of Claim.
The Board concurs with the Organization that it need not meet
an "exclusivity" test to advance its Claim to rail grinding work.
Form 1 Award No. 30180
Page 3 Docket No. MW-29523
94-3-90-3-469
However, the Carrier has established that outside forces have
performed rail grinding work over many years and have done so on
repeated occasions during the period that the Carrier's own rail
grinders were in operation. Further, the Carrier makes a credible
case that the Loram equipment here under review provides service
not obtainable from the Carrier's own equipment. On either of
these bases, the Board determines that the currently cited instance
of use of Loram equipment is not "within the scope of the
applicable schedule agreement" and thus not covered by Article 36.
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest:
2~!~
L1nda Woods - Arbitration Assistant
Dated at Chicago, Illinois, this 26th day of April 1994.