NATIONAL RAILROAD ADJUSTMENT BOARD
Form 1 THIRD DIVISION Award No. 30180
Docket No. MW-29523
94-3-90-3-469




PARTIES TO DISPUTE:

                  ((Eastern Lines)


STATEMENT OF CLAIM: "Claim of the System Committee of the
                  Brotherhood that:


      1. The Agreement was violated when the Carrier

          assigned outside forces to perform rail grinding

          work between Mile Post 815.2 at Bolen, Texas and

          Mile Post 736.9 at Sierra Blanca from July 31

          through August 5, 1989 (System File MW-89-97/485

          52-A SPE).


      2. The Agreement was further violated when the carrier

          failed to furnish the General Chairman with advance

          written notice of its intention to contract out

          said work as required by Article 36.


      3. As a consequence of the violations in Parts (1)

          and/or (2) above, Welding Foreman R.K. Lankford,

          Machine Operators H. R. Cordero, F. Fuentes and

          Machine Operator Helper E. Rodriguez shall each be

          allowed forty (40) hours of pay at their respective

          straight time rates and forty-one and one-half

          (41.5) hours of pay at their respective time and

          one-half rates."


FINDINGS:

The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:

.The carrier or carriers and the employe or employee involved in this dispute are respectively carrier and employe within the meaning of the Railway Labor Act as approved June 21, 1934.

This Division of the Adjustment Board has jurisdiction over the dispute involved herein.

Parties to said dispute waived right of appearance at hearing thereon.
Form 1 Award No. 30180
Page 2 Docket No. MW-29523
                                            94-3-90-3-469


At issue here is the Carrier's use of an outside contractor (Loram) to perform rail grinding work. There is no dispute that rail grinding work is performed by Maintenance of Way forces. The record is equally clear, however, that outside forces have been employed for rail grinding both prior to and concurrent with such work being undertaken by Carrier forces.


In response to a Claim concerning the contracting of such work, the Carrier stated in its April 6, 1990 letter to the organization as follows:


      "The Southern Pacific Transportation Company purchased two 40-stone rail grinders from Fairmont Railway Motors in the early 1980s to be used primarily to grind curves. [These are grinders operated by Carrier Maintenance of Way employees.] Prior to obtaining these grinders, all rail grinding was performed by outside forces. These two machines are presently combined to get better productivity and are working on the Western Lines. When the work there is completed, the combined machines will be moved to Del Rio, Texas, to grind the curves in West Texas.


      Recent tests have shown that the life of tangent rail can be prolonged with a consistent maintenance-based program of rail grinding. In order for this Carrier to implement such a program, it was necessary to obtain additional grinding capacity. Staring in 1989, we began using Loram Maintenance of Way, Inc. to perform additional rail grinding on both the Western and Eastern Lines. The grinding stones on the Loram equipment are hydraulically adjusted and computer controlled. This type of equipment is not owned by. any railroad in the United States. The rail grinding being performed by Loram could not be done by Carrier forces using our Fairmont equipment, as the magnitude of the program far exceeds the capacity of our equipment".


The Organization contends that, after the parties established rail grinding agreements, the Carrier "abolished the positions on its rail grinding train and ceased operation in 1989." This is at variance with the Carrier's contention of continued rail grinding operation by its forces. Whatever the facts may be, the question before the Board is whether the Carrier violated the notice provision of Article 36 and other Rules in its contracting specific rail grinding work to Loram as indicated in the Statement of Claim.


The Board concurs with the Organization that it need not meet an "exclusivity" test to advance its Claim to rail grinding work.

Form 1 Award No. 30180
Page 3 Docket No. MW-29523
94-3-90-3-469

However, the Carrier has established that outside forces have performed rail grinding work over many years and have done so on repeated occasions during the period that the Carrier's own rail grinders were in operation. Further, the Carrier makes a credible case that the Loram equipment here under review provides service not obtainable from the Carrier's own equipment. On either of these bases, the Board determines that the currently cited instance of use of Loram equipment is not "within the scope of the applicable schedule agreement" and thus not covered by Article 36.


                        A W A R D


      Claim denied.


                          NATIONAL RAILROAD ADJUSTMENT BOARD By Order of Third Division


Attest: 2~!~

      L1nda Woods - Arbitration Assistant


Dated at Chicago, Illinois, this 26th day of April 1994.