NATIONAL RAILROAD ADJUSTMENT BOARD
Form 1 THIRD DIVISION Award No. 30182
Docket No. MW-29552
94-3-90-3-494
The Third Division consisted of the regular members and in
addition Referee Herbert L. Marx, Jr. when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE*
(Southern Pacific Transportation Company
((Eastern Lines)
STATEMENT OF CLAIM: "Claim of the System Committee of the
Brotherhood that:
1. The Agreement was violated when the Carrier
assigned outside forces (Boh Brothers Construction
Company) to construct a waste water treatment
facility at mile Post 147 in the West Yard at
Lafayette, Louisiana beginning on or about August
31, 1989 and continuing (System File MW-89-110/485
89-A SPE).
2. As a consequence of the aforesaid violation, B&B
Foreman R.C. Lormand, Assistant Foreman G.W.
Viator, B&B Carpenters W. Stanford, L. Huval, D. P.
Barras, R.W. Sonnier, C.J. Arceneaux, Machine
operators C.L. Fontenot, N.D. Rideau, N.W. Sinegal,
H. Olivier and W. Williams shall each be allowed
pay at their respective rates for an equal
proportionate share of the total number of man
hours expended by the outside forces performing the
work in Part (1) above."
FINDINGS:
The Third Division of the Adjustment Board, upon the whole
record and all the evidence, finds that:
The carrier or carriers and the employe or employes involved
in this dispute are respectively carrier and employe within the
meaning of the Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over
the dispute involved herein.
Parties to said dispute waived right of appearance at hearing
thereon.
Form 1 Award No. 30182
Page 2 Docket No. MW-29552
94-3-90-3-494
By letter dated July 6, 1989, the Carrier notified the
organization as follows:
"Please accept this as Carrier's notice pursuant to
Article 36 of the BMWE Agreement of our intent to
contract out the following work:
Construction of new wastewater treatment
facility at Lafayette, Louisiana.
It is necessary to contract out this work as the
Carrier does not have the personnel, equipment or
expertise to construct this facility to meet EPA
specifications.
The work will begin on or after August 1, 1989".
The Organization requested a conference on the matter.
Following such conference, the Organization advised the Carrier by
letter dated July 19, 1989, in pertinent part as follows:
"During the conference you were advised that we are now
in a large force reduction on the Lafayette Division, you
were also advised that the Carrier owned or had under
lease all necessary equipment to perform this work and if
any other equipment was needed it could be rented without
operators in the Lafayette, Louisiana area.
During the conference you were advised that it was our
position that the Maintenance of Way forces did have the
expertise to perform all work involved in your notice.
You were advised that Maintenance of Way employees have
built or installed this type facility or similar
facilities at a number of locations on the Southern
Pacific and St. Louis Southwestern properties (Dallas,
Ennis, Fort Worth, Hearne, Houston, Pine Bluff and
Dalhart)".
The work in question was performed by an outside contractor
commencing August 31, 1989, and a timely Claim was initiated by the
organization.
A full review of the record convinces the Board that Carrier
arguments as to justification of the necessity of using outside
forces are not persuasive under the applicable Rules. Previous
performance of such work by Carrier forces was not denied. Indeed,
other than argument, the Carrier offered no evidence of
justification at all in the on-property handling of the dispute.
Form 1 Award No. 30182
Page 3 Docket No. MW-29552
94-3-90-3-494
The particular circumstances here demonstrate a lack of the
required "good faith" efforts to assign such work to Carrier
forces.
The question remains as the to the remedy, with the Carrier
contending that no monetary penalty is appropriate because the
claimants were under pay during the claimed period. The Board is
fully aware that previous Awards have examined the propriety of pay
depending on individual factual circumstances. Here, the Board
finds it would be an inadequate resolution simply to state that the
Carrier acted in violation of applicable Rules and will sustain the
Claim as presented.
A WAR D
Claim sustained.
NATIONAL RAILROAD
ADJUSTMENT BOARD
By Order of Third Division
Attest:
Linda Woods - Arbitration Assistant
Dated at Chicago, Illinois, this 26th day of April 1994.