NATIONAL RAILROAD ADJUSTMENT BOARD
Form 1 THIRD DIVISION Award No. 30186
Docket No. NW-28920
94-3-89-3-325
The Third Division consisted of the regular members and in
addition Referee Gil Vernon when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Union Pacific Railroad Company (former
' (Missouri Pacific Railroad Company)
STATEMENT OF CLALM: "Claim of the System Committee of the
Brotherhood that:
1. The carrier violated the Agreement when it assigned
outside forces to build partitions and rooms in the
depot at Coffeyville, Kansas on August 17 through
21, 1987 (Carriers File 870840 MPR).
2. The carrier also violated the Agreement when it
failed to give the General Chairman at least
fifteen (15) days* advance notice of its plan to
contract out the work described in Part (1) hereof.
3. As a consequence of the violations referred to in
either Part (1) and/or Part (2) hereof, B&B Foreman
J.A. Henderson, Assistant Foreman X.R. Cordray,
Mechanic G. Fisher, Helper J.A. LaFon and Motor Car
operator G.J. Durst shall each be paid ` ·. for an
equal proportionate amount each Claimant for eight
(8) hours each day plus overtime for August 17 -
21, 1987 account contractor worked (2) men.1"
FINDINGS:
The Third Division of the Adjustment Board, upon the whole
record and all the evidence, finds that:
The carrier or carriers and the employs or employes involved
in this dispute are respectively carrier and employe within the
meaning of the Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over
the dispute involved herein.
Parties to said dispute waived right of appearance at hearing
thereon.
Form 1 Award No. 30186
Page 2 Docket No. 1IW-28920
94-3-89-3-325
The parties to this dispute are subject to Article IV of the
May 17, 1968, Agreement which applies to contracting out. In the
case before the Board, the Organization protests the use of a
contractor to, essentially, remodel the depot at Coffeyville,
Kansas. In its initial claim, the organization asserted this work
was scope Rule covered and argued that advance notice was required.
The Carrier responded by providing a long list of projects in the
past where contractors were used without protest by the
organization. Eventually the organization provided a number of
statements from employees and former employees attesting to the
fact in the past they did a number of building projects.
The Board, after reviewing the record, is convinced of several
things. First, the organization has demonstrated enough history of
performing this particular type of work to convince us that, as a
general matter, it is entitled to advance notice for these kinds of
projects. However, we are also convinced that the organization has
slept on the right to notice for many years. Thus, given this
acquiescence, no remedy is appropriate for the lack of notice in
this case except to direct the carrier to comply with the notice
requirements in the future for projects of this nature. Where
there is a history and custom, not necessarily exclusively,
however, of employees performing certain work, notice is required.
of course, the fact notice is required does not mean contracting
out cannot take place. The ultimate propriety of the Carrier's
actions must be judged on the traditional criteria.
A W A R D
claim sustained in accordance with the Findings.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest:
Zh±~L
wh.4.
Linda Woods - Arbitration Assistant
Dated at Chicago, Illinois, this 26th day of April 1994.