Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 30199
Docket No. MW-29818
94-3-91-3-175
The Third Division consisted of the regular members and in
addition Referee Charlotte Gold when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO THE DISPUTE:
(Union Pacific Railroad Company
STATEMENT OF CLAIM: "Claim of the System Committee of the
Brotherhood that
(1) The Agreement was violated when the Carrier
assigned outside forces (C. M. Construction)
to construct the Carmen Locker and Lunchroom
Building at the Shop Facility at Pocatello,
Idaho beginning October 12, 1989 and
continuing (System File S-242/900179).
(2) As a consequence of the aforesaid violation,
Bridge and Building Foreman A. S. Kunz,
Carpenters M. S. Tilley, R. W. Tilley, T. D.
Stalder, R. E. Baker and C. L. Harris shall be
allowed compensation as follows:
`*** Claimant Kunz should be paid one hundred (100 hours
of straight time pay and eight (8) hours of time and onehalf (1 1/2) at the B&B foremans rate of
Harris and Baker should each be paid one hundred (100)
hours of straight time pay and eight (8) hours of time
and one-half (1 1/2) at the B&B first class carpenters
rate of pay, and Claimants Stalder, "'Tilley and Tilley
should each be paid one hundred (100) hours of straight
time pay and eight (8) hours of time and one-half (1 1/2)
at the B&B second class carpenters rate of pay, for
building work accomplished as of November 21, 1989. This
claim is considered continuous as the entire construction
of the building is work belonging Claimants because they
are Union Pacific Railroad Maintenance of Way Bridge and
Building Subdepartment Employes."'
FINDINGS:
The Third Division of the Adjustment Board, upon the whole
record and all the evidence, finds that:
The carrier or carriers and the employe or employes involved
in this dispute are respectively carrier and employe within the
meaning of the Railway Labor Act as approved June 21, 1934.
Form 1 Award No. 30199
Page 2 Docket No. MW-29818
94-3-91-3-175
This Division of the Adjustment Board has jurisdiction over
the dispute involved herein.
Parties to said dispute waived right of appearance at hearing
thereon.
This claim contests the work performed by an outside
contractor, C. M. Construction, on a new Carmen Locker and
Lunchroom in the Pocatello, Idaho, Shops area, commencing on
October 12, 1989. The organization alleges that this was typical
B&B construction work contractually reserved to its forces under
Rules 1, 2, 3, 4, 6, and 8 of the parties' Agreement, which it had
performed customarily.
On August 8, 1989, Carrier notified the General Chairman of
its intent to solicit outside bids. The Organization maintains
that solicitations for bids were sent prior to this Notice.
Regardless of whether Carrier had done so, it is only required to
give the Organization notice of its intent to subcontract. We view
this letter as constituting proper notice to the Organization. A
conference was held thereafter. When the matter was not resolved,
Carrier proceeded with the subcontracting. There is no dispute
that all of the claimants were fully employed during the time in
question.
Carrier argued in this instance, among other things, that it
did not have forces available at the time to do the work. This
Board is persuaded that that was in fact the case. Under the
provisions of Rule 52, this constituted a valid 'reason for
proceeding with the subcontract, notwithstanding the parties, other
arguments concerning whether the work was covered by the Scope
Rule, the weight of past practice by subcontracting, the
applicability of the exclusivity doctrine, and the like.
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By order of Third Division
Attest:
Linda Woods - Arbitration Assistant
Dated at Chicago, Illinois, this 8th day of June 1994.