Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 30216
Docket No. MW-29517
94-3-90-3-454
The Third Division consisted of the regular members and in
addition Referee Herbert L. Marx, Jr., when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(St. Louis Southwestern Railway Company
STATEMENT OF CLAIM: "Claim of the System Committee of the
Brotherhood that:
(1) The Agreement was violated when the Carrier
assigned an outside concern to perform the
work of clearing crossties from the right of
way between Corsicana and Tyler, Texas,
beginning on April 10, 1989. (System File MW89-27-CB/481-38-A)
(2) The Agreement was further violated when the
Carrier entered into a contracting transaction
without giving the General Chairman at least
fifteen (15) days advance written notice of
its plan to do so.
(3) As a consequence of the violations referred to
in either Part (1) and/or Part (2) above, the
Carrier shall pay furloughed employes W. D.
Brooks and L. R. Pannnell three hundred fortyfour (344) hours each at their respective
straight time rates of pay and eighty-six (86)
hours each at their respective time and onehalf overtime rates of pay and continuing so
long as the contractor performed the above
described track work."
FINDINGS:
The Third Division of the Adjustment Board, upon the whole
record and all the evidence, finds that:
The carrier or carriers and the employe or employes involved
in this dispute are respectively carrier and employe within the
meaning of the Railway Labor Act as approved June 21, 1934.
Form 1 Award No. 30216
Page 2 Docket No. MW-29517
94-3-90-3-454
This Division of the Adjustment Board has jurisdiction over
the dispute involved herein.
Parties to said dispute waived right of appearance at hearing
thereon.
This is a Claim on behalf of two furloughed employees in
connection with the removal by contractor's employees of scrap
crossties and other tie gang debris from the right-of-way between
Corsicana and Tyler, Texas, following work by a system tie gang on
such trackage.
The record convincingly demonstrates that the Carrier sold the
scrap crossties to the outside firm in an "as is, where is"
condition. This sale does not represent "contracting out" in any
sense contemplated by Article 33. Virtually identical findings
were reached in denial Third Division Award 28489 on the same
property. Third Division Award 29016, also under similar
circumstances on the property, was a sustaining Award solely on the
basis that, unlike here, the Carrier failed to present evidence
that a sale to the contractor had occurred.
As one of its arguments, the Organization suggests that the
sale was in fact a "sort of barter agreement" in that the ties were
sold at a price alleged to be below their actual value. This,
however, does not disturb the fact that the Carrier ceded ownership
of the material and was no longer in a position to contract the
work in its own interest.
With this conclusion, arguments raised by both parties as to
other aspects (lack of notice, Scope Rule, etc.) need not be
addressed.
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By order of Third Division
Attest:
&!,i,
Linda Woods - Arbitration Assistant
Dated at Chicago, Illinois, this 8th day of June 1994.