Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 30243
Docket No. SG-30876
94-3-92-3-716
The Third Division consisted of the regular members and in
addition Referee Joseph A. Sickles when award was rendered.
(Brotherhood of Railroad Signalmen
PARTIES TO DISPUTE:
(Consolidated Rail Corporation (CONRAIL)
STATEMENT OF CLAIM:
"Claim on behalf of the General Committee of the
Brotherhood of Railroad Signalmen (BRS) on the
Consolidated Rail Corporation (CONRAIL):
(A) Claim on behalf of P.A. Conrad, on account
Carrier violated the Signalmen's Agreement,
particularly the Scope Rule, when it permitted
non-agreement employees to perform Scope work
of shunting track circuits for signal tests on
February 26, 1991.
(B) Carrier should now be required to make
Claimant whole for the loss of overtime work
opportunity by compensating him for eight (8)
hours pay at his time plus one-half rate."
Gen'1. Chmn's. File No. RM2108-40-691.
Carrier's File No. SG-327. BRS File Case No.
8703-CR.
FINDINGS:
The Third Division of the Adjustment Board, upon the whole
record and all the evidence, finds that:
The carrier or carriers and the employe or employes involved
in this dispute are respectively carrier and employe within the
meaning of the Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over
the dispute involved herein.
Parties to said dispute waived right of appearance at hearing
thereon.
Form 1 Award No. 30243
Page 2 Docket No. SG-30876
94-3-92-3-716
The Scope Rule of the pertinent Agreement specifies:
"These rules shall constitute an agreement
between the Consolidated Rail Corporation and
its employees, represented by the Brotherhood
of Railroad Signalmen, covering rates of pay,
hours of service and working conditions of
employees in the classifications hereinafter
listed who are engaged, in the signal shop or
in the field, in the construction,
installation, repair, inspection, testing,
maintenance or removal of the following signal
equipment and control systems, including
component Parts, appurtenances and power
supplies (including motor generator sets) used
in connection with the systems covered by this
Agreement and all other work recognized as
signal work: (Emphasis added)
Interlocking systems
Block signal systems
Car retarder systems
Remote control of switch and
signal systems
Wayside train signals
Train order or train start signals
Cab signal, train control or train
stop systems other than that
portion on moving equipment
...
...Impedance bonds, signal
bonds and track connection leads".
On February 26, 1991, the General Inspector performed certain
tests by use of a shunt wire on the rails, which resulted in a
claim by the organization, on behalf of a signal maintainer.
The Carrier concedes that the Inspector was performing speed
and signal tests with the Transportation Department, to test the
efficiency of train and engine service employees in observing
Carrier operating rules.
The Carrier contended, while the matter was under review on
the property, that non-bargaining unit personnel had performed such
test historically: the claim was, at best, de minimis; and that the
signal maintainer Claimant was on duty and under pay at the time.
Form 1 Award
No. 30243
Page
3
Docket
No. SG-30876
94-3-92-3-716
The Organization denied that the claim was de minimis,
pointing out that a significant period of time was devoted to
performing the tests on the day in question. Moreover, it denies
the asserted historical utilization of non-bargaining unit
personnel to perform the work.
While the Scope Rule may have been determined in prior awards
to be general in nature, there is a certain degree of specificity
to the language of the Rule and the cited awards have given a
certain stature to the claim under consideration to the point that
it could be argued that the employee organization has established
a prima facie case, and that it is incumbent upon the Carrier to
establish its defenses by a preponderance of the evidence.
In any event, the handling on the property does not show
specificity concerning asserted past practices, nor is there
specific showing of the time involved regarding the "_d1 minimis"
argument. However, we have noted that the Carrier's arguments
referred to tests_ in the plural so that the Organization's
assessment at the time involved would not appear to be
unreasonable.
It is interesting to note in the awards cited by the
organization in its submission that, as far back as
1963,
Third
Division Award
No. 11507,
held that there was "no question" that
the installation of a temporary shunt is work on the signal system
circuit. That award cited Award No.
3688
for that same
proposition. See, also, Award No.
12627
and Award
No. 18384.
The
just-cited
1971
award specifically stated that:
"Those cases which have held that signalmen
were entitled to the work fall in two
categories, (1) where the sole activity
performed at the site where the shunt was
applied and the sole reason for being at the
site was the application of a shunt, and
(2)
where the shunt was used as the sole method of
protecting a particular block of track to
safeguard other work being done. An example
of the first would be where a shunt is applied
solely to test the readiness or efficiency of
train crews
...."
Form 1 Award No. 30243
Page 4 Docket No. SG-30876
94-3-92-3-716
As we have reviewed the facts of this case, they seem to fall
directly within the purview of the just-cited language. No awards
holding directly to the contrary have been brought to our
attention. As a result, we find that the organization has
demonstrated a showing of a violation and the Carrier has not
rebutted that showing, either on the merits or through a "de
minimis" application. The Claimant would have received overtime
had he been called to service and, within the concept of loss of
work opportunity, we will sustain the claim.
AWARD
Claim sustained.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest
Linda Woods - Arbitration Assistant
Dated at Chicago, Illinois, this 8th day of June 1994.
Carrier Member's Dissent
To
Award
30243
(Docket
SG-30876)
(Referee Sickles)
The Board's finding in this case is incorrect and ignores the fact that managerial
personnel have a long-standing history of applying track shunts while performing speed
checks. The Majority completely disregarded the Organization's burden of proof
requirement in this case. The Majority disregarded the fact that speed checks are not tests
of the Signal System and that a track shunt simply simulates the movement of a train.
The Signal System is not altered in any manner by the placing of a shunt between the
rails. The Majority is wrong, in the Carrier's opinion, when it holds that speed checks are
a test of the Signal System. Speed Checks are in fact tests that indicate whether train
crews are in compliance with Operating Rules; they are not signal tests. Applying a track
shunt between the rails performs the same function as if a train is on the tracks. There
is no alteration to the signals, in fact, it is a normal function of a track circuit to operate
under shunt conditions.
The sole reason that the Carrier's personnel were at the location was not to apply
the shunt, but to ensure that train crews were operating within the Rules. This
manipulation of the Signal System to perform crew performance checks has historically
been performed by non-BRS personnel. We therefore dissent.
P.V. Varga
V-41t -
M.W. Fingerhu
M.C. Lemik