Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 30267
Docket No. MW-30038
94-3-91-3-439
The Third Division consisted of the regular members and in
addition Referee Dana E. Eischen when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Union Pacific Railroad company (former
( Missouri Pacific Railroad Company)
STATEMENT OF CLAIM: "Claim of the System Committee of the
Brotherhood that:
(1) The Agreement was violated when the Carrier
assigned outside forces (Traylor and Sons
Contracting) with one (1) backhoe with an
operator and one (1) dump truck with an
operator to perform crossing work and to
install switch ties west from Marshall, Texas,
beginning April 26, 1990, and continuing
through June 22, 1990 (Carrier's File 900535
MPR).
(2) The Agreement was further violated when the
Carrier failed and refused to furnish the
General Chairman with advance written notice
of its intention to contract out said work as
required by Article IV and the December 11,
1981, Letter of Agreement.
(3) As a consequence of the violations referred to
in Parts (1) and/or (2) above, Red River
Division Trackman Driver J. G. Milton shall be
allowed, at his respective time and one-half
rate of pay, all time worked by the contractor
forces beginning April 26 through June 22,
1990."
FINDINGS:
The Third Division of the Adjustment Board, upon the whole
record and all the evidence, finds that:
The carrier or carriers and the employee or employees involved
in this dispute are respectively carrier and employee within the
meaning of the Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over
the dispute involved herein.
Form 1 Award No. 30267
Page 2 Docket No. MW-30038
94-3-91-3-439
Parties to said dispute waived right of appearance at hearing
thereon.
This dispute centers upon Carrier's alleged violation of the
Agreement when it "assigned outside forces to perform crossing work
and to install switch ties", and, "failed and refused to furnish
the General Chairman with advance written notice to contract out
said work.". Beginning April 9, 1990, through June 22, 1990,
Traylor and Sons Contracting performed crossing work and installed
switch ties west from Marshall, Texas, toward Grand Saline, Texas,
(MP 141 - 153). One backhoe and an operator and one dump truck and
an operator constituted contractor forces who worked "in
conjunction with" Carrier forces.
On June 25, 1990, the organization filed the following claim:
"Time is being claimed in behalf of Red River Division
Trackman Driver J. G. Milton, SSN 451-86-0872, beginning
April 26, 1990, at time and one-half rate and continuing
so long as Traylor and Sons Contracting performs
emergency work belonging to the Maintenance of Way
employes. Said contractor has been working West from
Marshall, Texas, preforming crossing work and installing
switch ties using one (1) backhoe with operator and one
(1) dump truck with operator.
This work which has traditionally and historically been
performed by Maintenance of Way employes and Carrier is
aware of the places where equipment can be procured if it
does not own the needed machinery. The American Railroad
Maintenance Equipment, Inc. Company of Mitchell,
Illinois, and the Victor L. Phillips Company of Kansas
City, Missouri, are two such places where Carrier can
obtain such needed equipment.
Therefore, it is our contention that Carrier is in
violation of certain Rules of our current Agreement,
especially Scope, Rules 1, 2, 10, 11, and 14. Carrier is
also in violation of Article IV of the May 17, 1968
National Agreement in that carrier failed to notify me as
General Chairman of the intent to contract the work in
question, and the December 11, 1981 letter of good faith
signed by Charles I. Hopkins, Jr., Chairman of the
National Railway Labor Conference, in which Carrier
agreed they would make good faith efforts to reduce sub
contracting and procure rental equipment to be operated
by Carrier employees."
Form 1 Award
No.
30267
Page 3 Docket
No.
MW-30038
94-3-91-3-439
Carrier denied the claim asserting that it was advanced
"without ample substance, and did not offer dates or locations
where the violation is claimed."
In subsequent correspondence, the Organization reasserted that
the work in dispute "is routine work normally performed by the
Maintenance of Way employes on a daily basis." The Organization
further submitted that if it was not possible to perform the work
in dispute during regular working hours, the work should have been
"made available to claimant Milton after regular working hours or
on weekends or his rest days."
In its reply, Carrier stated:
"At the outset, I am advised that this project began at
MP 141 on April 9, 1990, yet you failed to file your
claim until June 25, 1990. While in your original claim
you filed it as a continuing claim, obviously to avoid
any procedural argument, it nonetheless is noted in your
appeal you have asserted the claim period as being April
26 - June 22, 1990, and it was, therefore, not a
continuing claim but occurred during specific dates and
you were apparently aware of this at the time you filed
your claim. For the reason this is not a continuing
claim, your claim must be considered defective in
accordance with Agreement Rule 12."
Carrier further submitted that contractor forces were working
in conjunction with Carrier forces, and "assisted" with the work at
issue. Finally, Carrier argued that there are "no residual implied
restrictions" with respect to contracting out the disputed work,
and that Claimant was "fully employed throughout the claim period
and has not suffered the monetary loss you allege."
On June 25, 1990, the Organization filed a claim "beginning
April 26, 1990, at time and one half rate and continuing so long as
Traylor and Sons Contracting performs non-emergency work belonging
to the Maintenance of Way Employes." In this initial communication
the Organization asserted that the claim was a "continuing"
violation. However, in subsequent correspondence, the Organization
stated that the claim was time specific commencing April 26 and
continuing through June 22, 1990.
Form 1 Award
No.
30267
Page 4 Docket
No.
MW-30038
94-3-91-3-439
In correspondence dated November 19, 1990, Carrier submitted
that the work at issue had actually commenced on April 9, 1990,
rather than April 26, 1990. The organization did not dispute that
assertion in subsequent correspondence, nor did it dispute the fact
during a conference held later on the property. Therefore, this
Board must assume that the work in dispute did commence on April 9,
rather than April 26, 1990, as the Organization originally claimed.
According to Rule 12 of the Agreement, the Organization's June 25,
1990, claim was some two weeks tardy. This claim is dismissed.
AWARD
Claim dismissed.
0 R D B R
This Board, after consideration of the dispute identified
above, hereby orders that an award favorable to the Claimant(s) not
be made.
NATIONAL RAILROAD ADJUSTMENT BOARD
By order of Third Division
Dated at Chicago, Illinois this 19th day of July 1994.