Fri. 10/12/90 and Sat. 10/13/90 Fri. 10/19/90 and Sat. 10/20/90 Fri. 10/26/90 and Sat. 10/27/90 Fri. 11/02/90 and Sat. 11/03/90
10:30 PM to 6:30 PM 10:30 PM to 6:30 2M 10:30 PM to 6:30 PM 10:30 PM to 6:30 PM
The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:
The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the dispute involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
Sometime during the fall of 1990, Carrier determined that a radio antenna cable, suspended from the wall of its East New York tunnel, needed to be replaced. Due to the heavy volume of rail traffic through the tunnel during the week, it was decided that work on the project would be confined to weekend nights. Carrier .proceeded to schedule overtime on five weekends to complete the project. Rule 41 of the Agreement covers assignment of employees to pre-determined overtime. It provides:
The Organization contends that employees with the greates_ seniority were not given first opportunity to work overtime in t::e antenna cable replacement project, as Carrier utilized junior employees to Claimants as Foremen and as Signalmen in this overt:
work. Carrier denied the claim on the basis that the less sen:z: individuals that were used on overtime had worked on the pro;---_ prior to the overtime assignment.
Form 1 Award No. 30589The facts in this record do not support Carrier's arguments. While Carrier has offered evidence that perhaps some pre-project planning may have occurred for about one hour sometime before the project commenced, the evidence conclusively demonstrates that all of the work on the project was done on overtime. There is absolutely no showing that the scheduled overtime was a continuance of work performed prior to the overtime dates, so as to trigger the application of paragraph (c) of Rule 41.
An uncomplicated reading of Rule 41 indicates that when pre-determined overtime is to be worked, employees with the greatest seniority will be given first opportunity to do the work. If the conditions of paragraphs (a), (b) and (c) are not present, then seniority must prevail. Carrier has not demonstrated that the conditions of (a), (b) and/or (c) were present so as to permit the assignment of employees junior to Claimants to work on the project. Accordingly, the claim will be sustained.
Carrier has argued that if the claim is to be sustained, it had only ought to be at straight time rates, rather than overtime rates, as the Organization requests. This Division of this Board has long subscribed to the notion that when an employee is deprived of a work opportunity due to a Carrier violation of the agreement, the proper remedy is to make the employee whole for what he would have earned absent the violation. In Third Division Award 25601, the Board stated:
Award 25601 is sound and it will be followed here. Payment to Claimants to be made at time and one-half rates. (There is some indications in this record that some of the Claimants may have been paid a portion of the lost work hours in a settlement effort while the matter was being handled on the property. If this is the case, Carrier may deduct such settlement payments from the amounts due under this Award.)
This Board, after consideration of the dispute identified above, hereby orders that an award favorable to the Claimantls) be made. The Carrier is ordered to make the Award effective on or before 30 days following the postmark date the award is transmitted to the parties.