The Third Division of the Adjustment Board, upon the .nola record and all the evidence, finds that:
The carrier or carriers and the employee or employees invot,:ed in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction :err the dispute involved herein.
Parties to said dispute waived right of appearance at hearing thereon. Form 1 Award No. 30610
Claimant is a monthly rated Signal Inspector. His normal workweek is Monday through Friday, with assigned hours from 6:30 am to 2:30 pm. His monthly rate is based on 213 hours, and covers "all work subject to the Scope of the Agreement performed on the position to which assigned during the first five days of the work week." Sometime in November 1991, a track maintenance undercutting machine severed underground trunk cables in zone 5, disrupting train and crossing operations in that area. Claimant, along with a number of other Signal Department employees, was assigned to work on the repair and restoration of the signal and crossing devices. Claimant was on duty two hours beyond his scheduled quitting time on Tuesday, November 26, 1991. He seeks overtime pay for this service, on the basis that the work was not an emergency and he was required to perform tasks outside the scope of his normal duties of Signal Inspector.1
Carrier denies the Claim on the basis that Claimant is a monthly rated employee, the work was an emergency, and it was entitled to use him on the restoration of service project without additional compensation.
Rule 602 has two parts. The first provides that the monthly rate shall cover all work subject to the Scope of the Agreement (performed on the position to which assigned) during the first five days of the·-workweek. The second provides that the monthly rate shall cover work other than ordinary maintenance and construction work on the sixth day of the workweek (and on holidays).
11 The Statement of Claim mentions the "sixth day of his assignment," but this is not the case, as November 26, 1991 was a Tuesday. Form 1 Award No. 30610
With regard to the first part, "all work" can only be read to mean what it clearly states, the monthly rate would cover "all work subject to the Scope of the Agreement performed on the position to which assigned during the first five (5) days of the work week." During the first five days of the workweek, "all work" would include ordinary maintenance and construction work as well as work that would not be ordinary maintenance and construction work. With regard to the second part of the rule, the monthly rate would also include work other than ordinary maintenance and construction work performed on the sixth day and holidays.
Inasmuch as the work performed by Claimant was during the first five days of his workweek, to prevail in the overtime claim, it must be demonstrated that the work was not subject to the Scope of the Agreement performed on the position to which assigned during this first five days of the workweek. It makes no difference that the work may not actually be "other than ordinary maintenance and construction work," as argued by the Organization while the matter was being handled on the property, because, even if it where not work of this type, that consideration is only valid on the sixth day and on holidays. We are not dealing with either in this case.
Evidence is missing that the work performed by Claimant between 2:30 pm and 4:30 pm on November 26, 1991, was not subject to the Scope of the Agreement performed on the position to which Claimant was assigned. Instead the opposite is apparent. For
The work was obviously subject to the scope of the Agreement. Further, if~the work were continuous with the work performed during Claimant's regularly assigned hours, as the Organization states it was in therappeal, it is difficult to envision how it would not :;e performed on the position to which assigned during the first five days of the workweek. Form 1 Award No. 30610
Carrier has noted that the primary duties of the Claimant is testing and inspecting of signal systems. In this matter, once the cable was repaired, the system had to be tested. Claimant worked along side other signal forces in placing the system back into operations. To now provide additional compensation for working past the eighth hour when the monthly rate provides that it covers all work during the first five days of the workweek, would be to provide a benefit that the Organization was unsuccessful in securing through negotiations, it is argued. With this the Board concurs. The claim is without merit. It must be denied.
This Board, after consideration of the dispute identified above, hereby orders that an award favorable to the Claimant(s) not be made.