Form 1
NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 30683
Docket No. MW-30087
95-3-91-3-516
The Third Division consisted of the regular members and in
addition Referee Herbert L. Marx, Jr., when award was rendered.
PARTIES TO DISPUTE:
(Brotherhood of Maintenance of Way Employes
(Union Pacific Railroad Company (former
( Missouri Pacific Railroad Company)
STATEMENT
OF
CLAIM: "Claim of the System Committee of the Brotherhood that:
(1) TheAgreement was violated when the Carrier
assigned outside forces to perform the `. . .
cutting, and loading the ribbon rail onto a
rail train, . . knocking off rail anchors,
bagging rail anchors, straight railing
switches, and general clean up.* * *' from May
8 to May 31, 1990 and `In conjunction with
this project Marlatt Contracting has provided
the Carrier with two (2) 580 back hoes, and
two (2) employees for the purpose of digging
trenches along side each crossing where this
rail is to be laid on the Omaha Division main
line. T~.enches were dug between MP 419 to 411
on May 14, 15, and 16, on May 21, MP 415 to
406, and May 31, MP 406 to 399.38.'
(Carrier's File 900575 MPR).
(2) The below listed Claimants* shall each be
allowed at their respective rates of pay eight
(8) hours per day at the straight time rate,
and four (4) hours per day at the punitive
rate for May 8, 9, 10, 11, 14, 15, 16, 17, 18,
21, 22, 23, 24, 25, 28, 29, 30, 31 and twelve
(12) hours per day at the punitive rate for
May 12, 19 and 26, 1990.
*S.
K.
K.
F.
M.
W.
S. M.
R. Schaefer
E. Handke
S. Williams
L. Mueseler
W. Wilburn
E. Juilfs
Thomas
J. B. Van Nortwick D. B. Wilson
G. H. Hill C. L. Hop is
J. W. Moeck M.
F.
Petesch
J. S. Horton M. H. Hennigh
M. T. White R. L. Shorb
E. D. Bonebrake H. D. Gibbs"
Form 1 Award No. 30683
Page 2 Docket No. MW-30087
95-3-91-3-516
FINDINGS:
The Third Division of the Adjustment Board, upon the whole
record and all the evidence, finds that:
The carrier or carriers and the employee or employees involved
in this dispute are respectively carrier and employee within the
meaning of the Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over
the dispute involved herein.
Parties to said dispute waived right of appearance at hearing
thereon.
By letter dated March 15, 1990, the Carrier notified the
organization as follows:
"This is to advise you of the Carrier's intent to
solicit bids to cover the removal of track and all
appurtenances between M.P. 337.6 (Norkan Jct., Kansas)
and M. P. 403.8 (Vliets, Kansas) on the former portion of
the Concordia Branch.
This is the type of work that has customarily and
traditionally been performed by outside contractor's
forces. The Carrier has neither the skilled manpower nor
the proper equipment to safely and competently undertake
and complete this project in a timely manner. .
Following performance of indicated track removal, etc., the
organization challenged the Carrier's right to contract such work.
while the work is of a nature frequently performed by Carrier
forces, the record also shows a practice of contracting such work
over many years. In these circumstances, many Awards have supported the Carrier's right to contract
instances not relying on the Carrier's "exclusivity" argument).
Third Division Award 29714 stated:
"Numerous decisions of the Board have held that the
Carrier has the right under Article IV to contract out
work where advance notice is given and the Carrier has
established a mixed past practice of contracting out work
similar to that involved in the dispute. The record in
this case demonstrates a mixed practice on this property
with respect to the work in question. It has been
performed by members subject to the Agreement in the past
but has also been contracted out by the Carrier in the
past. We thus conclude that the Carrier did not violate
the Agreement when it contracted out the work."
Form 1 Award
No.
30683
Page 3 Docket
No.
MW-30087
95-3-91-3-516
Third Division Award 29792 is to similar effect, citing four
other previous Awards. Award 29792 sustained the Claim solely in
reference to the Carrier's failure to provide advance notice.
The organization contends that the advance notice (quoted
above) failed to mention "trench digging", which was part of the
work in reference to removing rails. This Board does not find this
sufficient, by itself, to reach a conclusion that the Agreement was
violated.
Beyond this, many previous Awards have supported a carrier's
contracting of work where the equipment and/or property is no
longer involved in railroad operations (as here) and when material
is sold on an "as is, where is" basis.
There is, however, one final aspect which requires review. In
this instance, the record is clear that the agreement between the
Carrier and the outside contractor calls for the Carriers'
retention of a substantial portion of the track and related
equipment for transportation to and use in carrier operations
elsewhere. The Carrier has provided no convincing argument that
the work of salvaging Carrier property for use elsewhere should not
or could not be readily performed by Carrier forces as part of
their regular and customary work assignments. Defenses as to past
practice, abandonment, sale of property simply are not convincing
as to this portion of the work.
Third Division Award 29873, although involving a different
carrier, discusses the difference between work on abandoned track
and the carrier's retention of portions of the track and equipment.
The parties are therefore directed to meet and agree on a
reasonable proportion of the hours expended by contractor forces
which are applicable to such salvage work (sorting, loading, etc.).
The Claim will then be sustained to this portion of the claimed
hours. In this instance, the Board concludes that monetary remedy
is required for lost work, despite the fact that Claimants were
actively on duty at the time.
AWARD
Claim sustained in accordance with the Findings.
Form 1 Award No. 30683
Page 4 Docket No. MW-30087
95-3-91-3-516
O R D E R
This Board, after consideration of the dispute identified
above, hereby orders that an award favorable to the Claimant(s) be
made. The Carrier is ordered to make the Award effective on or
before 30 days following the postmark date the Award is transmitted
to the parties.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Dated at Chicago, Illinois, this 31st day of January 1995.