Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 30783
Docket No. MW-30601
95-3-92-3-369
The Third Division consisted of the regular members and in
addition Referee Dana E. Eischen when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(CSX Transportation, Inc. (former
( Louisville and Nashville Railroad Company)
STATEMENT OF CLAIM:
"Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when Car
Shop employes were used to perform Track
Subdepartment work (cut weeds) in the track
and along the right of way at the north end of
the ID' Yard Lead and near the IL' Line at
Radnor Yard, Nashville, Tennessee on May 8,
1991. [System File 10(71)(91)/12(91-1087)LNR].
(2) As a consequence of the violation referred to
in Part (1) above, Messrs. J. R. Lackey, N. C.
Bess and R. D. Daniel shall each be paid eight
(8) hours' pay at their respective straight
time rates of pay for the time spent by the
Car Shop employes performing Track
Subdepartment work."
FINDINGS:
The Third Division of the Adjustment Board, upon the whole
record and all the evidence, finds that:
The carrier or carriers and the employee or employees involved
in this dispute are respectively carrier and employee within the
meaning of the Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over
the dispute involved herein.
Parties to said dispute waived right of appearance at hearing
thereon.
Form 1 Award No. 30783
Page 2 Docket No. MW-30601
95-3-92-3-369
This dispute, submitted to the Board by the Organization on
April 10, 1992, is a duplicate of the claim (Docket MW-30372)
submitted by the Carrier on February 12, 1992. The Board denied the
earlier submitted claim for failure of proof in Third Division
Award 30782. Based upon that decision, this claim is dismissed.
AWARD
Claim dismissed.
0 R D E R
This Board, after consideration of the dispute identified
above, hereby orders that an award favorable to the Claimant(s) not
be made.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division