Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 30825
Docket No. MW-30220
95-3-91-3-675
The Third Division consisted of the regular members and in
addition Referee Herbert L. Marx, Jr. when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Terminal Railroad Association of St. Louis
STATEMENT OF CLAIM: "Claim of the System Committee of the
Brotherhood that:
(1) The Carrier violated the Agreement when it assigned
or otherwise allowed outside forces (Oberkramer)
Construction Company) to perform digging work with a
backhoe at Track No. 56 on November 4, 1990. (System File
1990-029/013-293-16).
(2) The Agreement was further violated when the Carrier
failed to notify and discuss with the General Chairman
its intention to contract out said work as required by
Article IV and the December 11, 1981 Letter of Agreement.
(3) As a consequence of the violations referred to in
Parts (1) and/or (2) above, Large Machine Operator R.
Glenn shall be allowed two (2) hours and forty (40)
minutes' pay at his time and one-half rate."
FINDINGS:
The Third Division of the Adjustment Board, upon the whole
record and all the evidence, finds that:
The carrier or carriers and the employee or employees involved
in this dispute are respectively carrier and employee within the
meaning of the Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over
the dispute involved herein.
Parties to said dispute waived right of appearance at hearing
thereon.
As a Third Party at Interest, the Brotherhood of Railroad
Signalmen was advised of this dispute and submitted a response.
Form 1 Award No. 30825
Page 2 Docket No. MW-30220
95-3-91-3-675
On August 13, 1990, the Carrier notified the General Chairman
Of its intention "to contract a portion of the new construction of
track work for the project of by-passing the U.D. Connection Bridge
and the removal of the abandoned bridge". Conference was requested
and held concerning this project.
On November 4, 1990, a backhoe operated by an contractor's
employee was employed to excavate a ditch, permitting the Signal
Department to bury cable. This was apparently in relation to the
project discussed on August 29, 1990, although it obviously was not
specifically referenced in the notice.
There is dispute as to whether this work can properly be
claimed by Maintenance of Way forces or is work regularly performed
by Signalmen forces. The Board need not resolve this issue, since
other factors make this resolution unnecessary. The Carrier stated
during the claim handling process that the work here under review
was performed at the direction of the Union Pacific Railroad, which
was fully involved with the Carrier in the project, and that the
contract work was undertaken by the UP. The Board is not presented
with convincing evidence that this work was improperly under UP
control rather than under the Carrier's control. On this basis,
the Carrier cannot be found in violation of obligations under the
Agreement as to its own rights to contract work.
AWARD
Claim denied.
O R D B R
This Board, after consideration of the dispute identified
above, hereby orders that an award favorable to the Claimant(s) not
be made.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Dated at Chicago, Illinois, this 27th day of April 1995.