Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 30826
Docket No. MW-30221
95-3-91-3-676
The Third Division consisted of the regular members and in
addition Referee Herbert L. Marx, Jr. when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Terminal Railroad Association of St. Louis
STATEMENT OF CLAIM: "Claim of the System Committee of the
Brotherhood that:
(1) The Carrier violated the Agreement when it assigned
or otherwise allowed outside forces to construct a road
crossing over carrier tracks between Gratiot Street Tower
and 12th Street, in St. Louis, Missouri on December 7,
1990. (System File 1991-1/013-293-16).
(2) The Agreement was further violated when the Carrier
failed to notify and discuss with the General Chairman
its intention to contract out said work as required by
Article IV and the December 11, 1981 Letter of Agreement.
(3) As a consequence of the violations referred to in
Parts (1) and/or (2) above, Large Machine Operator J.
West shall be allowed seven and one-half (7.5) hours' pay
at his straight time rate."
FINDINGS:
The Third Division of the Adjustment Board, upon the whole
record and all the evidence, finds that:
The carrier or carriers and the employee or employees involved
in this dispute are respectively carrier and employee within the
meaning of the Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over
the dispute involved herein.
Parties to said dispute waived right of appearance at hearing
thereon.
Form 1 Award No. 30826
Page 2 Docket No. MW-30221
95-3-91-3-676
This claim is generally similar to that considered in Third
Division Award 30825 involving work related to the U. D. Connection
Bridge project. At issue here is the construction of a road
crossing over carrier tracks, which was carried out by Union
Pacific Railroad employees and a contractor.
There is no doubt that work of this nature, if undertaken by
the Carrier, is normally performed by Carrier forces. In this
instance, however, the organization had been notified of the
involvement of UP in the overall project, for its own purposes and
benefits.
As to the track crossing in question, the carrier notified the
General Chairman during the claim handling procedure as follows:
'The Union Pacific has a yard office opposite the
new track constructed by [the Carrier] and a second track
constructed by the UP. It was necessary for the Union
Pacific to construct a private crossing across the new
tracks to reach their yard office. The [Carrier] has no
need for this crossing and has no interest in installing
or maintaining it."
The Board is offered no evidence to contradict these
assertions. While the construction was necessarily performed with
the Carriers knowledge and consent, it was not for its benefit nor
did not it serve the Carrier's needs. On this basis, the Board
reaches the same conclusion as in Award 30825. Where work is under
control of and for the benefit other than the Carrier, the Carrier
cannot be required to meet Agreement restrictions as to its
performance.
AWARD
Claim denied.
9 R D E R
This Board, after consideration of the dispute identified
above, hereby orders that an award favorable to the Claimant(s) not
be made.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Dated at Chicago, Illinois, this 27th day of April 1995.