Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 30828
Docket No. MW-30226
95-3-91-3-683
The Third Division consisted of the regular members and in
addition Referee Herbert L. Marx, Jr. when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Terminal Railroad Association of St. Louis
STATEMENT OF CLAIM: "Claim of the System Committee of the
Brotherhood that:
(1) The Carrier violated the Agreement when it assigned
outside forces (Kamadulski Contracting Company) to
perform roadbed construction work near Gratiot Street in
St. Louis, Missouri, in connection with the Union Depot
track relocation project on September 4, 5, 6, 7, 10, 13,
14, 17, 19, 20, 21, 24, 25, 26, 27, and 28, 1990. System
File 1991-22/013-293-14).
(2) The Carrier violated the Agreement when it assigned
outside forces (Merit Construction Company) to perform
track construction work at Gratiot Street in St. Louis,
Missouri, in connection with the Union Depot track
relocation project beginning September 17 through
November 2, 1990. System File 1990-28/013-293-14).
(3) As a consequence of the violation referred to in
Part (1) above, Large Machine Operators R. Gray, D.
Stogner, R. Gower and R. Glenn shall each, in accordance
with their seniority, be allowed ten (10) hours' pay at
their applicable rate for each work day, September 4, 5,
6, 7, 10, 13, 14, 17, 19, 20, 21, 24, 25, 26, 27, and 28,
1990, the above described work was performed.
(4) As a consequence of the violation referred to in
Part (2) above, Foreman R. Gartner, Large Machine
Operators J. West and R. Gower, Truck Operators R.
Jackson, D. Schindler and O. Rodriquez and Track Laborer
M. Johnson shall each be allowed pay at their respective
rates for an equal proportionate share of the total
number of man hours expended by the outside forces
performing the above described work, retroactive sixty
(60) days from November 29, 1990."
Form 1 Award No. 30828
Page 2 Docket No. MW-30226
95-3-91-3-683
FINDINGS:,
The Third Division of the Adjustment Board, upon the whole
record and all the evidence, finds that:
The carrier or carriers and the employee or employees involved
in this dispute are respectively carrier and employee within the
meaning of the Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over
the dispute involved herein.
Parties to said dispute waived right of appearance at hearing
thereon.
The Carrier argues that the first claim set forth above should
be dismissed on procedural grounds because of the organization's
failure to notify the Carrier's representative of its rejection of
the reply of the Director, Labor Relations and Personnel within 60
days, as provided in Rule 42 (b). Rule 42 (c) provides, however,
that this requirement does not apply "in cases of appeal from the
decision of the highest officer designated by the Carrier to handle
such disputes". The Board finds no basis for procedural dismissal
of the Claim.
On August 13, 1990, the Carrier wrote to the General Chairman
in pertinent part as follows:
"Please be advised the Carrier intends to contract
a portion of the new construction of track work for the
project of by-passing the U.D. Connection Bridge and the
removal of the abandoned bridge. The new track to be
constructed will extend from Gratiot Street Interlock to
14th Street Interlock, across an open field not connected
to the operating railroad.
[Carrier] Track forces will be working on this
project. The magnitude of the project requires that all
areas of the project proceed simultaneously beyond the
capacity of our supervision, manpower and equipment.
After the new track is placed in service and the
present U.D. Connection Bridge is abandoned, it will be
sold in place for scrapping.
No Track or Bridge employees represented by BMWE are
furloughed."
Form 1 Award No. 30828
Page 3 Docket No. MW-30226
95-3-91-3-683
Conference was requested and held, and the carrier proceeded
with the project. At issue here, as stated by the Organization, is
the Carrier's use of contract forces to "perform basic track
construction work on the Gratiot Street track relocation project"
and certain track construction work at Gratiot Street.
As to the use of machines by a contractor in the first cited
instance, the Carrier advised the organization during the claim
handling process as follows:
"On the dates claimed, all large machine operators
were fully employed, operating Company owned equipment
and working overtime. This project required additional
equipment which the Carrier does not own. The contractor
worked on building a new road bed not connected to the
operating railroad. At the completion of the extra new
construction work, the contractor was released. The
connections were made by Carrier employees."
As to the second claim, the Carrier advised as follows:
".
. . six (6) additional Track employees were
hired: no BMWE employees were furloughed: and Track
employees were worked excessive overtime to accomplish
this project, in addition to extra help by outside
contract forces supplementing supervision, labor and
equipment."
The Board finds no convincing refutation to these accounts.
While the work involved is such regularly performed by Maintenance
of Way forces, the fact remains that the Carrier advised the
Organization of its intentions: made the fullest use of all
available employees, including additions to the force: did not have
its own equipment available to cover all of the work; and was
working under time constraints to complete the overall project. In
these circumstances, the Board concludes that some contracting was
unavoidable and that Carrier forces would not have been available
within the required time and thus were not deprived of work.
AWARD
Claim denied.
Form 1 Award No. 30828
Page 4 Docket No. MW-30226
95-3-91-3-683
O R D 8 R
This Board, after consideration of the dispute identified
above, hereby orders that an award favorable to the Claimant(s) not
be made.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Dated at Chicago, Illinois, this 27th day of April 1995.