Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 30829
Docket No. MW-30227
95-3-91-3-684
The Third Division consisted of the regular members and in
addition Referee Herbert L. Marx, Jr. when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Terminal Railroad Association of St. Louis
STATEMENT OF CLAIM: "Claim of the System Committee
of
the
Brotherhood that:
(1) The carrier violated the Agreement when it assigned
outside forces (Hulcher Contracting Company) to install
panelized switches at Gratiot Street in St. Louis,
Missouri on September 29, October 2 and 3, 1990. System
File 1990-26/013-293-14).
(2) The Agreement was further violated when the Carrier
failed to properly notify and discuss with the General
Chairman its intention to contract out said work as
required by Article IV and the December 11, 1981 Letter
of Agreement.
(3) As a consequence of the violations referred to in
Parts (1) and/or (2) above, Foreman R. Gartner, Large
Machine Operators R. Gower and D. Stogner and Track
Laborers C. Wicks and C. Perry shall each be allowed
sixteen (16) hours, pay at their respective straight time
rates and eleven (11) hours' pay at their respective time
and one-half rates."
FINDINGS:
The Third Division of the Adjustment Board, upon the whole
record and all the evidence, finds that:
The carrier or carriers and the employee or employees involved
in this dispute are respectively carrier and employee within the
meaning of the Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over
the dispute involved herein.
Parties to said dispute waived right of appearance at hearing
thereon.
Form 1 Award No. 30829
Page 2 Docket No. MW-30227
95-3-91-3-684
This dispute concerns work involved in the major construction
project reviewed in Third Division Award 30828, which is
incorporated herein by reference. At issue here is the
"installation of track switch panels" by forces employed by a
contractor.
In defense of its action, the Carrier advised the organization
during the claim handling procedure as follows:
"All BMWE represented employees, including the above
claimants, were fully employed and working twelve (12)
hours per day, seven (7) days per week. This contractor
provided a side-boom cat that is not owned by (the
Carrier], nor can the ownership of one be justified.
Only one cat was used, with one operator . . . ."
The reasoning in Award 30828 is equally applicable here.
There is no basis to find that the Claimants could have been
utilized for this work, while simultaneously being assigned to the
fullest extent on the same project.
AWARD
Claim denied.
0 R D E R
This Board, after consideration of the dispute identified
above, hereby orders that an award favorable to the Claimant(s) not
be made.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Dated at Chicago, Illinois, this 27th day of April 1995.