Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 30830
Docket No. MW-30256
95-3-91-3-728
The Third Division consisted of the regular members and in
addition Referee Herbert L. Marx, Jr. when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES
TO
DISPUTE:
(Union Pacific Railroad Company (former
( Missouri Pacific Railroad Company)
STATEMENT OF CLAIM: "Claim of the System Committee of the
Brotherhood that:
(1) The Agreement was violated when the Carrier
assigned outside forces (Marlatt Contracting) to build a
new siding at Mile Post 401 in the vicinity of Stella,
Nebraska on September 4, 5, 6, 7, 10, 11, 12, 13, 14, 17,
18, 19, 20, 21, 24, 25, 26, 27, 28, October 1, 2, 3, 4,
5 and 9, 1990 (Carrier's File 910122 (MPR).
(2) The Carrier also violated Article IV of the May
17, 1968 National Agreement when it failed to furnish the
General Chairman with advance written notice of its
intention to contract out said work.
(3) As a consequence of the violations referred to
in Parts (1) and/or (2) above, Foremen R. D. Underwood
and E. D. Bonebrake (furloughed) and Machine Operators R.
Z. Duran, G. E. Breen and K. D. Eichelberger (furloughed)
shall each be allowed eight
(e)
hours' pay per day at
their respective straight time rates of pay plus any
overtime worked by the contractor's forces on the dates
listed in Part (1) above."
FINDINGS:
The Third Division of the Adjustment Board, upon the whole
record and all the evidence, finds that:
The carrier or carriers and the employee or employees involved
in this dispute are respectively carrier and employee within the
meaning of the Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over
the dispute involved herein.
Form 1 Award No. 30830
Page 2 Docket No. MW-30256
95-3-91-3-728
Parties to said dispute waived right of appearance at hearing
thereon.
This claim concerns the construction by other than Carrier
forces of a new siding at Mile Post 401 in the vicinity of Stella,
Nebraska, in September-October 1990. The
organization contends
that this work should properly have been assigned to Maintenance of
way forces.
The Carrier's primary defense is that the work involved was
performed for and under the direction and control of an industrial
client, which had entered into an agreement
concerning a
facility
adjacent to the Carrier's right-of-way. During the claim
handling
procedure, the General Chairman was provided with an Industry Track
Agreement, dated September 14, 1990, between the Carrier and the
industry. This agreement makes specific reference to the right of
the industry to construct "at its expense" the trackage
concerning
which the claim was initiated. There is no showing of any
relationship between the Carrier and the contractor who performed
the work for the industry.
The
organization responds
that the work actually began ten
days prior to the date of such agreement and that the agreement
fails to make clear any abdication of the Carrier's responsibility
for the track.
The Board determines, however, that the Carrier's assertion as
to lack of control of the contracting is adequately supported by
the cited Industry Track agreement. Where a carrier cannot be
shown to be responsible for or in control of construction or
related work, there can be no application of the contractual
conditions and restrictions (including advance notice) which apply
where the Carrier is responsible and in control.
AWARD
Claim denied.
O R D E R
This Board, after consideration of the dispute identified
above, hereby orders that an award favorable to the Claimant(s) not
be made.
Form 1 Award No. 30830
Page 3 Docket No. MW-30256
95-3-91-3-728
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Dated at Chicago, Illinois, this 27th day of April 1995.