Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 30897
Docket No. MW-28017
95-3-87-3-574
The Third Division consisted of the regular members and in
addition Referee Edwin H. Benn when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Duluth, Missabe and Iron Range Railway
( Company
STATEMENT OF CLAIM: "Claim of the System Committee of
the Brotherhood that:
(1) The Carrier violated the Agreement when it
assigned outside forces to repair the BNSaunders Bridge beginning on or about May 1986
(System Claim 34-86)
(2) As a consequence of the aforesaid violation,
the Carrier shall:
' . pay the amount of hours of each employee
hired by the contractor during the length of
time the contractor is on the property. This
time will be divided by the amount of
employees furloughed on the Missabe Division
in the fall or latter part of the summer while
employed on this Division during the length of
time the contractor was on the property. In
the event no employees are furloughed the
amount will be divided between all employees
working in the Proctor headquarters
jurisdiction at the time the contractor is on
the property. Also, the furloughed employees
benefits will be extended to include Blue
Cross and days credited towards their vacation
requirements. This is on account of their
loss of work opportunity and monetary
losses."
FINDINGS:
The Third Division of the Adjustment Board, upon the whole
record and all the evidence, finds that:
The carrier or carriers and the employee or employees involved
in this dispute are respectively carrier and employee within the
meaning of the Railway Labor Act as approved June 21, 1934.
Form 1 Award No. 30897
Page 2 Docket No. MW-28017
95-3-87-3-574-
This Division of the Adjustment Board has jurisdiction over
the dispute involved herein.
Parties to said dispute were given due notice of hearing
thereon.
By letter dated October 23, 1985, the Carrier notified the
organization that it was going to employ a contractor to perform
certain abutment repairs to the Burlington Northern bridge at
Saunders, Wisconsin on the Interstate Branch. With that notice,
the Carrier advised the organization of the following specifics:
"It is the intention of the DM&IR to complete Phase I
repairs to the abutments of the BN Bridge over the DM&IR
tracks at Saunders, Wisconsin before the end of the year.
These repairs will permit continuation of BN traffic over
the bridge at reduced speeds until April or May of 1986
when additional and more permanent repairs will be made
(Phase II work).
Phase I work consists primarily of the installation of 72
reinforcing steel dowels approximately 28 feet long -- 35
in the south abutment and 37 in the north. The dowels
are to be grouted in with epoxy resin. In addition, the
bearing seats must be cleaned; the first construction
joint down from the top of the abutments must be cleaned
and grouted; wood shims are to be inserted behind the
bridge beams; and temporary steel diaphragms must be
removed and replaced.
Due to the critical nature of the work, the specialized
techniques, equipment and materials to be utilized, and
in consideration of potentially cold weather conditions
and schedules to be met, the DM&IR intends to contract
for the installation of the dowels and the cleaning and
grouting of the construction joints. By means of the
contract, the work by contractor is also guaranteed.
DM&IR personnel will clean the bearing seats, place wood
shims behind the bridge beams, remove and replace the
steel diaphragms, and provide flagging as required for
DM&IR train movements.
The time to perform the above described work before very
cold weather sets in is extremely short and the DM&IR
intends to proceed as rapidly as possible to complete the
work before the end of the year."
Form 1 Award No. 30897
Page 3 Docket No. MW-28017
95-3-87-3-574-
According to the Carrier, the Phase I repairs began on
December 13, 1985 and were completed on January 28, 1986 with the
work performed by an outside contractor to the extent specified in
the October 23, 1985 notice. No claims were filed by the
organization with respect to the Phase I work.
The dispute in this matter concerns Phase II. At a conference
on March 7, 1986, the carrier informed the organization of its
intention to contract further repairs at the BN-Saunders Bridge.
By letter dated March 12, 1986, the Carrier informed the
organization in detail about its intentions:
"A. Description of Work to be Contracted
The concrete abutments for this structure have
failed by cracking and displacement over a
period of years, and must be repaired to
retain the structural integrity of the bridge.
The contractor would provide all material,
labor, equipment and supervision to perform
comprehensive repairs to the bridge while
maintaining rail traffic both on and under the
bridge. This would be done by performing work
on a part of the superstructure (carrying the
BN traffic) at a time, thus leaving two of the
present four tracks in service while replacing
and repairing the superstructure and
substructure in the area of the other two
tracks. Estimated train traffic over this
bridge consists of 15 to 17 trains per 24hour-period and under the bridge at 10 to 12
trains per 24-hour-period: work will have to
be coordinated and carefully controlled to
advance the work under these traffic
conditions. The proposed repairs to the
abutments consist of the construction of 17
horizontal steel bracing struts below the
track level, and of four horizontal concrete
reinforced struts at the top of the abutment
walls to provide lateral support from one side
of the abutment to the other. Installation of
these struts insures that the back wall
embankment soil pressure is transmitted
through the back walls will brace each
other. In addition, because of the age
and condition, and construction of the
steel superstructure, it is less costly to
replace the superstructure than to remove,
repair and reinstall the existing structure.
Form 1 Award No. 30897
Page 4 Docket No. MW-28017
95-3-87-3-574
Consequently, new steel framing members will
be installed as a part of this project. The
existing steel will be retained for salvage by
the contractor and handled as scrap material
from the job site.
B. Reasons for Work to be Contracted.
This work involves a number of different
aspects such as demolition of existing
concrete, removal and dismantling of the
existing steel structure, removal and
replacement of the timber decking; removal of
grout, placement of heavily reinforced
concrete sections across the face of each
abutments, forming, placing rebar and pouring
concrete struts from top to top of the
abutments; excavation, placement of fabric,
PVC drain pipe, steel ties, Elastomeric
bearing pads, poured-in-place concrete struts
below the tracks and extreme coordination
required of the contractor with all the
railroads involved, both at the bridge level
and lower track level. The work area is
extremely compact, the bridge length is
approximately 36' and the vertical height from
DMIR track to bottom of structure
approximately 22'. Marshaling areas adjacent
to the work site are limited and placement of
specialized work equipment such as cranes, air
compressors, concrete trucks and fabricated
new steel will all have to be studied and
executed with precision to make the work move
ahead properly and promptly. Staging area for
receipt of incoming material and removal of
outgoing material is limited and will also
have to be carefully utilized and scheduled.
The work involves knowledge in a full range of
construction skills by workmen who have great
proficiency and experience in each of the
areas where the knowledge and ability are
required. It is essential that because the
bridge structure has already failed, that the
work proceed promptly and accurately so that
no other further failure might occur.
Form 1 Award No. 30897
Page 5 Docket No. MW-28017
95-3-87-3-574-
According to the Carrier, a contractor was awarded the job on
May 5, 1986. Phase II commenced June 2, 1986 and was completed on
August 7, 1986. The claim in this matter was filed on June 3,
1986.
Supplement No. 3, Paragraph (a), mandates that the Carrier
'. . will make every reasonable effort to perform all maintenance
work in the Maintenance of Way and Structures Department with its
own forces.' Supplement No. 3, Paragraph (b), further states that
'Consistent with the skills available in the Bridge and Building
Department and the equipment owned by the Company, the Railway
Company will make every reasonable effort to hold to a minimum the
amount of new construction work contracted.'
The Carrier asserts that due to the magnitude and complexity
of Phase II, the work was beyond the skills available in the
Maintenance of Way employees' group in general and the Bridge and
Building forces in particular and, as such, the Carrier complied
with the mandate in Supplement No. 3 that it make "every reasonable
effort" to have its employees perform the work. The Organization
asserts that the employees were capable of performing the work and
possessed the necessary skills and experience to do the job.
This Board has no doubt (and the record supports the
conclusion) that with respect to the individual components of the
Phase II work on the BN-Sounders Bridge, the Carrier's employees
possessed the skills, ability and knowledge necessary to accomplish
those tasks and, on an individual basis, competently performed
those tasks in the past.
But, the record shows that the Carrier had to undertake a very
complex repair operation on the highly traveled and much in need of
repair BN-Sounders Bridge. That high traffic bridge was in a
state of disrepair which could not be prolonged. The record shows
that repair of the bridge mandated an immense commitment of
manpower, required the use of several items of equipment not owned
by the carrier (drilling machine, grout pump, demolition equipment,
pile driver and crane), called for detailed coordination of traffic
to permit the repairs to go forward expeditiously and involved
limited areas for the staging of equipment and materials. The
Organization has not sufficiently demonstrated that the Carrier has
performed sufficiently similar complex jobs in the past with the
use of Carrier forces. Due to the over-all magnitude and
complexity of the job and the constraints involved, we are
satisfied that using a contractor to perform the work was
permissible under the circumstances and not prohibited by
Supplement No. 3.
Form 1 Award No. 30897
Page 6 Docket No. MW-28017
95-3-87-3-574.
AWARD
Claim denied.
0 R D E R
This Board, after consideration of the dispute identified
above, hereby orders that an award favorable to the Claimant(s) not
be made.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Dated at Chicago, Illinois, this 8th day of June 1995.