Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 30900
Docket No. MW-29113
95-3-89-3-547
The Third Division consisted of the regular members and in
addition Referee Edwin H. Benn when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Consolidated Rail Corporation
STATEMENT OF CLAIM: "Claim of the System Committee of
the Brotherhood that:
(1) The Agreement was violated when the Carrier
assigned outside forces (Loram, Inc.) to
perform roadbed maintenance work (cleaning
ballast) on the Western Branch between
Ridgeway and Bowling Green, Ohio and on the
Cleveland to Indianapolis Main Line between
Ridgeway and Bowling Green, Ohio from July 5
through July 23, 1988 (System Docket MW-108).
(2) The Agreement was further violated when the
Carrier failed to give the General Chairman
fifteen (15) days' advance written notice of
its intention to contract out said work.
(3) As a consequence of the violations referred to
in Parts (1) and/or (2) above, three (3)
senior Columbus Division machine operators on
furlough during the claim period shall each be
allowed one hundred seventy (170) hours of pay
at their straight time rates."
FINDINGS:
The Third Division of the Adjustment Board, upon the whole
record and all the evidence, finds that:
The carrier or carriers and the employee or employees involved
in this dispute are respectively carrier and employee within the
meaning of the Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over
the dispute involved herein.
Form 1 Award No. 30900
Page 2 Docket No. MW-29113
95-3-89-3-547
Parties to said dispute waived right of appearance at hearing
thereon.
On the dates set forth in the claim, the carrier utilized a
contractor (Loram Company) to clean ballast by removing dirt and
replacing the cleaned stone back on the roadbed. The carrier
defended its actions on the grounds that the contractor had been
used by the Carrier since approximately 1970 performing the same
work over the Carrier's entire system through use of the
contractor's Shoulder Ballast Cleaners (which the contractor only
allows its personnel to operate) without the Carrier giving
notification to the organization and without prior complaint by the
organization.
Assuming for the sake of discussion that the Organization's
arguments are all contractually correct, (i.e., that notice was
required and not given and that the work fell within the purview of
the scope rule), nevertheless, on the basis of the evidence before
us, this claim must be denied.
In the past, and without prior objection by the Organization,
the Carrier extensively utilized a contractor to perform the work
in dispute. The lack of objection by the organization for similar
kinds of action effectively lulled the Carrier into presuming that
such contracting out was permissible. Under the circumstances, no
affirmative relief could be awarded even assuming that the
carrier's assumption was contractually incorrect.
WA ARD
Claim denied.
O R D $ R
This Board, after consideration of the dispute identified
above, hereby orders that an award favorable to the Claimant(s) not
be made.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Dated at Chicago, Illinois, this 8th day of June 1995.