Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 30975
Docket No. MW-30063
95-3-91-3-476
The Third Division consisted of the regular members and in
addition Referee Dana E. Eischen when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(CSX Transportation, Inc. (former
( Seaboard System Railroad)
STATEMENT OF CLAIM: "Claim of the System Committee of
the Brotherhood that:
(1) The Carrier violated the Agreement when,
without a conference being held between the
Chief Engineering Officer and the General
Chairman, as required by Rule 2, it assigned
or otherwise permitted outside forces [six (6)
employes of American Railroad Construction
Company] to perform the maintenance work of
dismantling and constructing 830 linear feet
of trackage at or near Mile Post ANB 862.5 on
the Manchester Subdivision of the Atlanta
Division beginning March 26, 1990 up to and
including April 5, 1990 [System File 9057/12(90-647) SSY].
(2) As a consequence of the aforesaid violation,
Foreman E.L. Thompson and Trackmen C.
Patton,Jr., G.P. Hollmon, B. L. Reeves, E.T.
Howell and A.T. Ray shall each be allowed pay
at their respective straight time and overtime
rates for an equal proportionate share of the
total number of straight time man-hours (480)
and overtime man-hours (60) expended by the
outside forces performing the work outlined in
Part (1) above."
FINDINGS:
The Third Division of the Adjustment Board, upon the whole
record and all the evidence, finds that:
The carrier or carriers and the employee or employees involved
in this dispute are respectively carrier and employee within the
meaning of the Railway Labor Act as approved June 21, 1934.
Form 1 Award No. 30975
Page 2 Docket No. MW-30063
' 95-3-91-3-476
This Division of the Adjustment Board has jurisdiction over
the dispute involved herein.
Parties to said dispute waived right of appearance at hearing
thereon.
There is essentially no dispute as to the facts of this case.
As part of its "Proctor Creek" project, the Metropolitan Atlanta
Rapid Transit Authority ("MARTA") constructed a tunnel under
Carrier's right-of-way. MARTA's project necessitated the
relocation of Carrier's main line trackage at or near MP ANB 862.5
to accommodate tunnel construction. Thus, 830 feet of new track
was constructed for Carrier adjacent to the existing main line
trackage.
MARTA contracted American Railroad Industries, Inc., whose
forces installed the 830 feet of new track. Once this new track
was completed, Carrier forces performed the work of cutting off the
existing main line track and connecting the new track to the
existing main line alignment at the north and south ends. American
Railroad Industries, Inc. employees then dismantled the "cut out"
trackage after the newly constructed track was connected to the
existing main line alignment by Carrier's forces.
On May 25, 1990, the organization filed a claim for six
employees for the work performed by employees of American Railroad
Industries, Inc., between March 26 up to and including April 5,
1990.
Carrier denied the claim maintaining that:
"The work that was allegedly done by an outside party as
indicated in your claim, was done under the direction of
MARTA. However, MARTA constructed the track adjacent to
the mainline which was NOT connected to any active or
live track. Once this track was finished, CSX's forces
physically cut the track and connected the new track to
the existing alignment. All of this work was done by CSX
employees including surfacing. After the old track
alignment was cut out of the live track, the outside
party disassembled the track. As you can see, the
Agreement was not violated in any shape, form, or
fashion. This claim is declined."
The Organization similarly appealed the claim asserting:
Form 1 Award No. 30975
Page 3 Docket No. MW-30063
95-3-91-3-476
"In Mr. Delong's letter he readily admits that the
Contractor did indeed perform the maintenance work made
subject of our claim.
Rule 2 of the effective Agreement is quite clear and
states,
`This Agreement requires that all maintenance
work in the Maintenance of Way and Structures
Department is to be performed by employees
subject of this Agreement except that it is
recognized that, in specific instances,
certain work that is to be performed requires
special skills not possessed by the employees
and the use of special equipment not owned or
available to the Carrier. In such instances,
the Chief Engineering Officer and the General
Chairman will confer and reach an
understanding setting forth the conditions
under which the work will be performed.'
With regard to the above quoted Rule, Carrier forces, the
Claimants, were available to perform this work. They
possessed the necessary skills and had the proper
equipment available to perform this subject work. Even
if they had not, the Carrier failed in its mandated
obligation to confer with the General Chairman."
Parties to the dispute met in conference without wavering from
respective positions taken in correspondence previously exchanged
on the property. Therefore, the dispute has been placed before the
Board for resolution.
The Organization made out a prima facie case that outside
forces performed work to which its members were entitled. Carrier
asserted, but did not prove that the entire project "belonged" to
MARTA, and that the Carrier had "no control" over the use of
outside forces. It was incumbent upon the Carrier to submit
probative evidence supporting its assertion that the work of
constructing 830 feet of new main line track and dismantling the
old main line track was "performed under the total authority and
for the sole benefit of MARTA." We are persuaded that the
construction of the new track was instigated by MARTA and that
Carrier had no control over its subcontracting; but the Carrier has
not carried its burden of proof regarding the dismantling of the
old main line on its own property. Aside from bare assertions,
there is no probative evidence on the record to justify Carrier's
failure to use its own forces to dismantle the old main line. At
Form 1 Award No. 30975
Page 4 Docket No. MW-30063
95-3-91-3-476
a minimum, Carrier was clearly obligated to confer with the General
Chairman prior to contracting out said work. To that extent,
therefore, this claim must be sustained. This Board shall retain
jurisdiction over the question of appropriate damages should the
Parties be unable to agree upon the time spent by the subcontractor
in dismantling and removing the old track.
AWARD
Claim sustained in accordance with the Findings.
ORDER
This Board, after consideration of the dispute identified
above, hereby orders that an award favorable to the Claimant(s) be
made. The Carrier is ordered to make the Award effective on or
before 30 days following the postmark date the Award is transmitted
to the parties.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Dated at Chicago, Illinois, this 26th day of July 1995.