Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 31030
Docket No. MW-30195
95-3-91-3-643
The Third Division consisted of the regular members and in
addition Referee Edwin H. Benn when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Union Pacific Railroad Company
STATEMENT OF CLAIM: "Claim of the System Committee of
the Brotherhood that:
(1) The Agreement was violated when the Carrier
assigned an outside concern (Pioneer Roofing
Company) to install a new roof at the Diesel
Shop, Salt Lake City, Utah beginning on June
28, 1990 and continuing (System File 5350/900583).
(2) The Agreement was further violated when the
Carrier failed to provide the General Chairman
advance written notice of its intention to
contract out the work involved here in
accordance with Rule 52.
(3) As a consequence of the violations referred to
in either Part (1) and/or Part (2) above, Utah
Division B&B Carpenters S. K. Stuart, D. A.
Holt, B. L. Holt and J. L. Smith shall each be
allowed pay for an equal proportionate share
of the total number of straight time and
overtime man-hours expended by the contractor
forces at their applicable straight time and
overtime rates of pay."
FINDINGS:
The Third Division of the Adjustment Board, upon the whole
record and all the evidence, finds that:
The carrier or carriers and the employee or employees involved
in this dispute are respectively carrier and employee within the
meaning of the Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over
the dispute involved herein.
Form 1 Award No. 31030
Page 2 Docket No. MW-30195
95-3-91-3-643
Parties to said dispute waived right of appearance at hearing
thereon.
Without giving the organization prior notice of its intent to
do so, the Carrier contracted out the replacement of a roof at the
Diesel Shop, Salt Lake City, to Pioneer Roofing Company. Work
commenced June 28, 1990.
Rule 52 requires advance notice be given to the organization:
"... In the event the Company plans to contract out work
because of one of the criteria described herein, it shall
notify the General Chairman of the Organization in
writing as far in advance of the date of the contracting
transaction as is practicable and in any event not less
than fifteen (15) days prior thereto ...."
Because of the lack of notice of its intent to contract out
the work, the Carrier violated Rule 52. Third Division Award 23578
('Rule 52 uses the mandatory term 'shall' and notice is required
regardless of whether or not the erection of earth mounds for
signal facilities is historically, traditionally, and customarily
performed by Maintenance of Way employes.').
We are not satisfied that an emergency existed warranting the
operation of the exculpatory emergency language in Rule 52
(requiring notice 'except in 'emergency time requirements' cases').
The deteriorating condition of the roof was known by the Carrier
for quite some time prior to its contracting out the work.
According to the Carrier on the property, leakage was experienced
during the winter of 1989-1990 and spring storms brought about
further leakage. The work did not begin until June 28, 1990.
While the condition of deterioration of the roof may have had
potentially dangerous effects, given the history of the
deterioration of the roof, this was not the kind of event that
needed sudden and immediate attention. On the property, the
organization asked the proper questions:
"... [I]f a true emergency situation existed, common
sense tells us that you would want to eliminate the
condition as soon as possible. You indicate in your
letter that the leaking of the roof occurred as early as
1989 and continued through the spring of 1990. If it was
an emergency, why did the Carrier wait until June and
July of 1990 to have the work performed? Why did the
Carrier not have the contractor perform the work on
Sunday? Is the Carrier suggesting it postponed the
purported emergency during the 6 to 9 months before the
work was performed ....?"
Form 1 Award No. 31030
Page 3 Docket No. MW-30195
95-3-91-3-643
Taken to its logical extent, the failure to maintain any
structure or piece of equipment could have potentially dangerous
ramifications and every maintenance function would become an
emergency. The exception carved out for emergencies in Rule 52
would then swallow up the rule. We must find that no emergency
existed.
With respect to the remedy, the carrier is correct that
ordinarily on this property monetary relief is awarded for
contracting out violations only when employees are on furlough.
See e.g., Third Division Award 29308. But, for lack of notice
situations, see Third Division Award 23578:
"A long line of Third Division Awards precludes us from
providing the claimants with pecuniary relief where they
have not proved loss of work opportunity or loss of
earnings due to the Carrier's failure to tender the
required notice unless the Carrier has flagrantly or
repeatedly failed to comply with Rule 52. See Third
Division Awards No. 23354 (Dennis) ; No. 21646 (Ables);
No. 20275 (Eischen) No. 20671 (Eischen); No. 18305
(Dugan). In this case we do not find any evidence of a
malicious motive underlying the Carrier's failure to give
the Rule 52 notice.
While we must deny the claimant's request for monetary
damages, we expect the carrier, in the future, to fully
and properly comply with the Rule 52 notice provisions."
See also, Third Division Award 26174:
"At the same time, we are also persuaded by the decision
in Award 23354, that compensation must be denied because
all affected employees are fully employed and suffered no
loss. This is a position that has long been applied in
the industry and we find no basis for ruling to the
contrary. This is not to say, however, that there is no
merit to the organization's contention that flagrant and
continued disregard of a Carrier's responsibility to
provide proper notification should result in the
sustaining of a monetary Claim. It is an argument that
warrants attention and we will continue to consider it in
the future."
Form 1 Award No. 31030
Page 4 Docket No. MW-30195
95-3-91-3-643
Subsequent to the issuance of Third Division Awards 23578 and
26174, this Board has had the opportunity to consider the scope of
the remedy on this property in cases were notice is not given in
accord with the requirements of Rule 52. See e.g., Third Division
Awards 30286, 30066, 29310. Those more recently decided cases have
specifically limited relief in lack of notice cases to employees
who were on furlough. We find those recent awards are not palpably
erroneous and, for purposes of stability, must be followed.
Therefore, the monetary relief requested in this case shall be
limited to employees on furlough, if any.
AWARD
Claim sustained in accordance with the Findings.
O DE
This Board, after consideration of the dispute identified
above, hereby orders that an award favorable to the Claimant(s) be
made. The Carrier is ordered to make the Award effective on or
before 30 days following the postmark date the Award is transmitted
to the parties.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Dated at Chicago, Illinois, this lst day of September 1995.