Form 1
NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 31049
Docket No. MW-30135
95-3-91-3-574
The Third Division consisted of the regular members and in
addition Referee Hugh G. Duffy when award was rendered.
PARTIES TO DISPUTE:
STATEMENT
OF CLAIM:
(Brotherhood of Maintenance of Way Employes
(
(Southern Pacific Transportation Company
( (Western Lines)
"Claim of the System Committee of
the Brotherhood that:
(1) The Agreement was violated when the carrier
assigned outside forces (Fairmont Railway
Motors) to perform switch grinding work on the
San Joaquin Division near Tehachapi,
California beginning June 4, 1990 and
continuing (System File #2/MofW 152-1141 SPW).
(2) The Agreement was further violated when the
Carrier failed to furnish the General Chairman
with advance notice of its intention to
contract out said work as required by Article
IV of the May 17, 1968 National Agreement.
(3) The claim as presented by former General
Chairman D.E. McMahon, on August 30, 1990 to
Superintendent R.A. Baker, shall be allowed as
presented because said claim was not
disallowed by the Superintendent in accordance
with Rule 44.
(4) As a consequence of the violations in Parts
(1) and/or (2) and/or (3) above, the Claimants
listed below shall each be allowed twelve (12)
hours' pay at the grinder operator's rate of
pay sixty (60) days retroactive from the date
of the initial claim.
W. Clark, Jr.
J.S. Ledesma
T.C. Clemens
D.R. Hawthorns
E.C. Bourgeois
J.H. Porras
R.L. White
R.N. Jones"
Form 1 Award No. 31049
Page 2 Docket No. NW-30135
95-3-91-3-574
FINDINGS:
The Third Division of the Adjustment Board, upon the whole
record and all the evidence, finds that:
The carrier or carriers and the employee or employees involved
in this dispute are respectively carrier and employee within the
meaning of the Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over
the dispute involved herein.
Parties to said dispute waived right of appearance at hearing
thereon.
In this claim, filed on August 30, 1990, the organization
alleges that the Carrier violated the Agreement when it assigned
outside forces to perform switch grinding work on the carrier's San
Joaquin Division, beginning June 4, 1990 and continuing. The claim
is closely linked to a similar claim filed on July 23, 1990, which
was the subject of Third Division Award 30751, in that it involves
the same Claimants, the same kind of work performed by outside
contractors, and the same period of time during which the work was
performed. Award 30751 concerned rail grinding work performed on
the Sacramento Division, and the instant case concerns switch
grinding work performed on the San Joaquin Division, both beginning
on June 4, 1990.
The merits of this dispute have been previously determined in
Third Division Award 30180, where the Board concluded as follows:
"The Board concurs with the Organization that it need not
meet an `exclusivity' test to advance its Claim to rail
grinding work. However, the carrier has established that
outside forces have performed rail grinding work over
many years and have done so on repeated occasions during
the period that the Carrier's own rail grinders were in
operation. Further, the carrier makes a credible case
that the Loram equipment here under review provides
service not obtainable from the Carrier's own equipment.
On either of these bases, the Board determines that the
currently cited instance of use of Loram equipment is not
`within the scope of the applicable schedule agreement'
and thus not covered by Article 36."
Form 1 Award No. 31049
Page 3 Docket No. NW-30135
95-3-91-3-574
The Organization contends, however, that this claim must be
sustained on the procedural basis that the claim was not disallowed
by the Carrier in a timely manner pursuant to Rule 44. The Carrier
contends that it made a timely denial of the August 30, 1990 claim
by letter of October 18, 1990, although that letter incorrectly
refers to the July 23, 1990 claim.
The Board addressed the identical procedural issue in
previously-referenced Award 30751:
"The Organization seeks to have the claim sustained on a
procedural basis. The claim herein was initially filed
under date of July 23, 1990. On October 1, 1990, the
Organization wrote to the Carrier stating that it had
received no reply to the claim and seeking to have the
claim 'allowed as presented', as provided in Rule
44(1)(a). The Carrier replied stating that it had
replied in timely fashion on August 24, 1990, and
attached a copy of such letter.
The Board notes this is one of a number of closely
similar claims initiated within a narrow time frame. The
Board is prepared to accept that a timely carrier
response was prepared on August 24, 1990. Difficult or
impossible to determine is whether it was properly
dispatched and/or whether it was received and coordinated
with the applicable claim. Thus, failure to comply with
Rule 44 is not sufficiently demonstrated.
The dispute involves the contracting of rail grinding
work. This subject was fully discussed in Third Division
Award 30180, and the Board reaches the same conclusion in
this instance."
We find this Award to be of direct precedential value in the
instant dispute, and accordingly will resolve the procedural issue
in this case in the same manner. We therefore conclude that the
claim must be denied.
AWARD
Claim denied.
Form 1 Award No. 31049
Page 4 Docket No. MW-30135
95-3-91-3-574
ORDER
This Board, after consideration of the dispute identified
above, hereby orders that an award favorable to the Claimant (s) not
be made.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Dated at Chicago, Illinois, this 1st day of September 1995.