NATIONAL RAILROAD ADJUSTMENT BOARD
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Chicago, Central and Pacific Railroad Company
STATEMENT OF CLAIM: As shown in Docket No. MW-32220 and not
repeated herein.
FINDINGS: The Third Division of the Adjustment Board finds:
That the dispute was certified to the Third Division of the
Adjustment Board ex parte by the petitioning party; and
Under date of July 25, 1995, the petitioning party addressed
a formal communication to the Arbitration Assistant requesting
withdrawal of this case from further consideration by the Division
which request is hereby granted.
AWARD
Claim withdrawn.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Dated at Chicago, Illinois, this lst day of September 1995.