This Division of the Adjustment Board has jurisdiction over the dispute involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
From September 4 through October 9, 1990, the Carrier undertook removal of contaminated soil by milepost 89 within Stockton Yard as a part of the installation of a locomotive diesel oil containment system. To this end, the Carrier engaged the services of an outside firm, using equipment to remove the contaminated soil. The record fails to show proof that more than one employee of the outside contractor was used for this purpose.
The Organization argues that the Carrier failed to give the requisite notice under Article IV of the May 17, 1968 National Agreement and further denied Carrier forces the opportunity to do work which they claim to regularly perform.
Of direct interest here is that three of the four claimants were directly involved in assisting with the outside contractor's work in the contaminated soil removal, while the fourth Claimant was fully occupied elsewhere.
The Carrier defends its action by asserting the work "was not exclusive" to maintenance of way employees and that the work performed "was not for the benefit of the Carrier but in compliance with state environmental agencies' regulations." Exclusivity is not a test which must be met to determine whether work should be performed by a craft or classification claiming the work rather than by an outside contractor. Nor are these reasons sufficient to negate the requirement that the Carrier comply with Article IV as to advance notice, which it failed to do here.
Thus, the Carrier is in violation of its fundamental obligation to provide advance notice of subcontracting. Where the work involved is at least arguably of a nature which has been and can be performed by the Claimants, a monetary remedy is frequently in order. Here, however, the Board must take note that at least three of the Claimants were actively at work with tag emolovee 91 = subcontractor. It thus must be concluded that there was no loss of work opportunity on their part, and no way their part of the work could have been deferred to another time. In this instance, additional wage payment would not be appropriate.
The Board sustains Sections (1) and (2) and denies Section (3) of the claim. Form 1 Award No. 31149
This Board, after consideration of the dispute identified above, hereby orders that an award favorable to the Claimant(s) be made. The Carrier is ordered to make the Award effective on or before 30 days following the postmark date the Award is transmitted to the parties.