Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 31172
Docket No. MW-30789
95-3-92-3-575
The Third Division consisted of the regular members and in
addition Referee Margo R. Newman when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Union Pacific Railroad Company
STATEMENT OF CLAIM: "Claim of the System Committee of the
Brotherhood that:
(1) The Agreement was violated when the Carrier
assigned outside forces (Gilbert Central
Corporation) to perform Maintenance of Way and
Structures Department work (setting forms,
tieing rebar, pouring and finishing concrete,
installing anchor bolts in concrete, removing
forms and cleaning debris) at the Eastbound
Locomotive Servicing Facility in North Platte,
Nebraska beginning on February 18, 1991 and
continuing (System File S-511/910535).
(2) As a consequence of the violations referred to
in Part (1) above, Group 3 Foreman K. E.
Peterson and
B&B Carpenters
D. T. McIntosh, R.
K. Hughes, J. P. Nila, J. W. Gurwell, J. B.
Martinez and J. A. Meyer shall each be allowed
compensation, at their respective rates of
pay, for the loss of work opportunity suffered
for an `*** equal proportionate share of the
man hours worked by the employees of the
outside contracting force from February 18,
1991 ... and continuing until this violation
of the Agreement no longer exists. ***'"
FINDINGS:
The Third Division of the Adjustment Board, upon the whole
record and all the evidence, finds that:
The carrier or carriers and the employee or employees involved
in this dispute are respectively carrier and employee within the
meaning of the Railway Labor Act as approved June 21, 193`.
Form 1 Award No. 31172
Page 2 Docket No. MW-30789
95-3-92-3-575
This Division of the Adjustment Board has jurisdiction over
the dispute involved herein.
Parties to said dispute waived right of appearance at hearing
thereon.
This dispute arises out of the Carrier's use of outside forces
to perform concrete work as part of a large scale remodeling
project on a locomotive service facility in North Platte, Nebraska.
While the organization argues that the Carrier did not serve notice
in this case until February 26, 1991, after the concrete work had
begun on February 18, 1991, the claim does not include an
allegation of a notice violation, and the record reflects that
notice was initially served covering concrete work on this project
on June 13, 1990, and was conferenced on July 16, 1990. Thus, there
is no valid contention before this Board that the notice provisions
of Rule 52(a) were violated.
The record in this case demonstrates a mixed practice on this
property with respect to the concrete construction work in
question, which has been confirmed in prior Awards of the Board.
Third Division Awards 30287, 30262 and 28623. Numerous decisions of
the Board have held that the Carrier has the right to contract out
work under Rule 52 (b) and (d) where advance notice is given and the
Carrier has established a mixed past practice. We conclude that the
Carrier did not violate the Agreement when it contracted out the
work.
AWARD
Claim denied.
ORDER
This Board, after consideration of the dispute identified
above, hereby orders than award favorable to the Claimant(s) not be
made.
NATIONAL RAILROAD ADJUSTMENT BOARD
By order of Third Division
Dated at Chicago, Illinois, this 26th day of September 1995.