The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the dispute involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
This case involves an application of the provisions of Rule 5 - WORK WEEK which reads as follows:
This Board's review of the on-property claim handling as well as a consideration of the respective submissions reveals that this dispute involves a single Signal Inspector position whose assigned rest days were changed from Saturday and Sunday to Sunday and Monday. There is nothing in the case record from either party relative to exactly when this change occurred. There is nothing from either party to explain the break in the claim period. Claim No. 1 covers April 18 to June 29, 1992. Claim No. 2 covers July 27 to August 8, 1992. There is nothing from either party to explain Carrier's assertion in their submission to the Board that "Claimant's position, that of Signal Inspector, was assigned rest days of Sunday and Monday so as to provide better coverage with other Signal Inspectors." What other Signal Inspectors? Where? What rest days? None of this is answered. Form 1 Award No. 31298
The Board's review of the case record has determined that Carrier has indeed made a prima facie case that the several Signal Crews employed on their Suburban Division were arranged with staggered rest days to accommodate the work which was being performed by those crews. However, having said that, we are faced here with a single independent Signal Inspector position which, according to Carrier's position during the on-property handling of the dispute, -1. . works directly with Signal Crews, as he performs tests on the various projects constructed by the Signal Crew. Claimant's work days were therefore changed from Monday through Friday to Tuesday through Saturday in order to correspond with the Signal Crew." The Signal Crews, however, according to Carrier's submission to the Board had as rest days Friday and Saturday (2 crews), Saturday and Sunday (3 crews) and Sunday and Monday (2 crews). This begs the unanswered question, which crew did the Signal Inspector work directly with? There is no explanation to be found in the case record.
There is no real question in the mind of the Board relative Carrier's right to create staggered work weeks or to deviate from a Monday-Friday work week where the nature of the work requyres six or seven days of service each week. What is in dispute in this situation is carrier's unilateral right to assign other than Saturday and Sunday as rest days on a 5-day position where the duties of that position "can reasonably be met in five days."
The Board is not impressed with the Organization's argument relative to the necessity to create relief assignments. That is not an issue in this case. The Board is, however, impressed with the logic expressed in Third Division Award 13834 which held that "when managerial judgment is challenged, it is the obligation of management to supply evidence by which this Board can decide if that judgment was proper."
In this case, the Organization has repeatedly challenged Carrier's position relative to the independent nature of this Signal Inspector position. Carrier has failed to show that the Signal Inspector work was, in fact, performed on more than five days per week. Carrier has not shown by probative evidence that Signal Inspector work was performed on Sundays or Mondays. Carrier has not shown by probative evidence that any other Signal Inspector encountered a change of rest days or that any other Signal Inspector performed service as such in this territory on Sundays or Mondays. It is the Board's conclusion, on the basis of this case record, that the Signal Inspector position here in question was, in fact, a 5-day position and as provided by Rule 5(b) entitled to have Saturday and Sunday as rest days. Form 1 Award No. 31298
As to the remedy sought in this dispute which is additional one-half time for service performed by Claimant on Saturdays plus 8 hours straight time for work not performed on Mondays during the respective claim periods, the Board is of the opinion that the conclusion reached in Award 2 of Public Law Board No. 4716 is applicable in this instance. Therefore, it is the Board's conclusion here that Claimant is not entitled to any additional payment for the Mondays of the claim periods on which he did not work. He is, however, entitled to payment of the additional one-half time for service performed on the Saturdays during the claim periods which he would have received for work on his rest day but for Carrier's improper changing of the rest days.
This Board, after consideration of the dispute identified above, hereby orders that an Award favorable to the Claimant be made. The Carrier is ordered to make the Award effective on or before 30 days following the postmark date the Award is transmitted to the parties.