The Third Division consisted of the regular members and in addition Referee Gerald E. Wallin when award was rendered.
The Third Division of the adjustment Board, upon the whole record and all the evidence, finds that:
The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the dispute involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
This dispute comprises ten individual one-day pay claims by six different claimants for dates from May 12 through may 23, 1991. Although they are all similar, some differences exist between some of the claims. In general, however, they each allege that Carrier failed to fill temporary vacancies, due to the incumbent's vacation absence, with Agreement-covered train dispatchers. Form 1 Award No. 31345
This dispute raised a procedural issue that requires resolution before reaching the substantive merits. In essence, the Organization contends that the claims must be allowed as presented because Carrier failed to comply with the time limitation requirements of Rule 17.
After the claims were initially denied , nine were appealed to Carrier's Manager of Labor Relations on June 17, 1991. The tenth was appealed on June 24, 1991. Each appeal letter concluded with this paragraph:
The Manager's letter did not provide any information regarding dates on when the asserted scheduling discussion occurred. Nor did the manager's letter assert that there was an agreed upon extension of Rule 17 time limits.
In its next correspondence, the Organization maintained its position that the claims were in default under Rule 17. The parties discussed the claims in conference on November 21, 1991 and agreed to return the claims to the local level for further discussion. However, the Carrier's November 26th conference report explicitly states the parties agreed that the remand was "... without prejudice to our respective positions on the conference scheduling requirements of Rule 17(b)."
On February 18, 1992, Carrier formally denied each of the claims on the merits. Its denials did not mention the procedural issue remaining in dispute.
Following conference on July 24, 1992, Carrier wrote on September 10, 1992, again denying the claims on the merits. It also said:
In subsequent correspondence on the property, neither party retreated from its position on the time limits issue.
Rule 17 contains ten subdivisions. The first three include multiple references to 60-day limitations for the taking of action by one party or the other. Subdivision (e) also provides for extension of the applicable time limits by agreement. When read in its entirety, Rule 17 contemplates that the various claim handling activities will occur within 60-day intervals unless extensions are agreed upon. Indeed, even the Carrier's September 10, 1992 letter suggests an acknowledgment that normally conferences are held within 60 days of the appeal.
Given the manner in which the procedural issue is postured here, Carrier's position is, effectively, an affirmative defense. Accordingly, it has the burden of proof to establish the validity of its position. In its Ex-Parte Submission, the Carrier maintained only the aspect of its position that the time limit was automatically extended by virtue of the Organization's request for a conference. It did not continue to maintain that it had undertaken efforts to schedule a conference within the 60-day limit.
If Carrier's contention, regarding automatic extension, is taken to its logical conclusion, there would never be a time limit on its response to the Organization's appeals as long as it did not actually participate in a conference. If Carrier were so inclined, it could resist agreeing to a conference indefinitely and, thereby, interminably delay the claims process. Nothing in the language of Rule 17 explicitly supports such a result or the automatic time limits extension that the Carrier advocates. Quite to the contrary, Rule 17 (e) provides only for extensions by agreement. Accordingly, it is determined that Carrier has failed to sustain its burden of proof to establish its position. Form 1 Award No. 31345
If, as Carrier once contended on the property, it encountered difficulty in properly scheduling a conference, Carrier could have requested an extension of time limits. Even Carrier does not say it did so. In the alternative, Carrier could have issued a denial, to protect time limits, until a conference date could be agreed upon with the allegedly "indifferent,, Organization representatives. Carrier did not avail itself of this tactic either. Indeed, the record does not establish that carrier actually took any action whatsoever to advance the claim handling process under Rule 17 within 60 days of the appeals. On the evidence, it must be concluded that Carrier essentially ignored these claims until the Organization drew attention to them.
Under the circumstances, we must sustain the claims under the default language of Rule 17 (b). While we prefer to see claims decided on their merits, where possible, we are not free to ignore the provisions of Rule 17 of the parties Agreement as they have applied it. Our decision, it should be noted, is subject to the compensation limitation established by Rule 17 (g) and the nonprecedence provisions of Rule 17(j).
Because these claims are decided on procedural grounds, we do not reach their merits.
This Board, after consideration of the dispute identified above, hereby orders that an award favorable to the Claimant(s) be made. The Carrier is ordered to make the Award effective on or before 30 days following the postmark date the Award is transmitted to the parties.