This Division of the Adjustment Board has jurisdiction over the dispute involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
At the outset, the Organization protests new evidence and arguments offered by the Carrier in its submission to the Board. No material not considered by the Parties on the property will be considered in the Board's deliberations.
By letter of October 17, 1991, Carrier notified the Organization that it intended to contract out repair work on Carrier's newly-acquired MacArthur Bridge in St. Louis, Missouri. In its letter, Carrier stated that it did not have the necessary equipment for making the repairs, and that the state of the bridge was sufficiently hazardous to constitute an emergency. Carrier requested a waiver of the required fifteen day advanced notification. By letter of October 22, 1991, the Organization denied Carriers request for the waiver and requested a conference on the matter. On November 4, 1991, having received no response from the Carrier, the Organization contacted Carrier to ascertain the status of the work on MacArthur Bridge. The Parties ultimately held a conference on the matter on November 22, 1991. The contracting work began on December 5, 1991.
In a letter dated December 11, 1991, the organization filed a claim on requesting payment for eight hours straight time and two hours overtime for each day the outside contractor worked on the bridge repairs. Carrier denied the claim, and it was subsequently progressed in the usual manner including conference on the property, after which it remained unresolved.
At issue in this case is application of Article IV-Contracting Out of the Agreement of May 17, 1968, to which each Party is signatory. Article IV reads in pertinent part as follows:
Carrier maintains that it complied in full with Article IV. Further it disputes the organization's position that the work at issue was reserved to B&B employees. Finally, Carrier reiterates that the situation involved constituted an emergency.
In light of the fact that work on the bridge actually began more than a month and one-half after the initial letter from Carrier to the General Chairman, this Board does not find credible Carrier's protest that the situation in question constituted an "emergency°. Accordingly, it was obliged to comply in good faith with the provisions of Article IV. Carrier relies on the fact that the work in question was not begun until December 5, 1991, as evidence that it complied in good faith with Article IV. Form 1 Award No. 31346
However, the record indicates that Carrier did not confer with the Organization until after it had contracted with outside forces to perform the bridgework, and the contractor's equipment was already on Carrier property. By no stretch of the imagination can such actions be considered as proceeding "in good faith." Accordingly, the Board finds that Carrier did violate Article IV of the May 17, 1968 Agreement.
Carrier's position that no BMWE employees were furloughed at the time the outside contract was signed is without merit. There is unrefuted evidence on this record that, once the work was actually begun on December 5, 1991, all of the Claimants except one had, in fact, been furloughed.
With respect to the remainder of the claim, except for assertions, the organization has presented no evidence to contradict Carrier's statement that it did not have the equipment to perform the work at issue. However, nowhere has the Carrier refuted the Organization's assertion in its letter of October 22, 1991, that but for operation of the "special" equipment, B&B employees are entitled to the work being performed under Rule 2 of the Agreement. Rule 2 specifically describes the work of the various job titles listed. (See, for example, Third Division Award 29007. It clearly defines a B&B Mason and Concrete mechanic as "... an employe assigned in connection with construction, maintenance and dismantling of concrete, brick and stone portions of bridges.") Moreover, in Carrier's initial letter to the General Chairman, it proposed absence of furloughed B&B employees as part of its rationale for contracting out the work in the first place. While the work was actually being performed, however, B&B employees were furloughed. Further, at no time during the processing of this claim on the property did Carrier refute the Organization's position that the work was reserved to B&B employees.
Carrier is correct, however, that the organization has not made a showing that all nine Claimants listed would, or could have worked on the job in question. Accordingly, the amount of compensation must be limited to the number of Claimants equal to the number of contractor employees actually doing B&B work. Payment shall be made only to those claimants who, but for Carrier's violation, would have been called to work on the days in question, and only for the number of hours worked by the contractor's employees.
This Board, after consideration of the dispute identified above, hereby orders that an award favorable to the Claimant(s) be made. The Carrier is ordered to make the Award effective on or before 30 days following the postmark date the Award is transmitted to the parties.