The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:
The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the dispute involved herein.
Parties to said dispute waived right of appearance at hearing thereon. Form 1 Award No. 31360
The facts in this record disclose that between March 8, 1993 and March 12, 1993, several employees were assigned the task of clearing away crossties at the 14th Street Plant, St. Louis, Missouri. One of the employees assigned held Bridge and Building seniority. The Organization contends that the work was Track Department work and, therefore, only employees with Track Department seniority should have been used.
Upon review of the applicable cited Agreement provisions, this Board is inclined to agree with the Organization. The claim will be sustained, however, only for the equivalent amount of time that the B&B employee was assigned. The total hours worked by the B&B employee will be divided between the two Track Department Claimants.
This Board, after consideration of the dispute identified above, hereby orders that an award favorable to the Claimant(s) be made. The Carrier is ordered to make the Award effective on or before 30 days following the postmark date the Award is transmitted to the parties.