NATIONAL RAILROAD ADJUSTMENT BOARD
Form 1 THIRD DIVISION
Award No. 31523
Docket No. MW-30595
96-3-92-3-359
The Third Division consisted of the regular members and in addition Referee
Edwin H. Benn when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Consolidated Rail Corporation
STATEMENT OF CLAIM: "Claim of the System Committee of the
Brotherhood that:
(1) The Agreement was violated when the Carrier assigned outside
forces (James White Construction Company) to perform construction of
retaining walls at Mile Posts 20.0 to 22.7, on the Monongahela Secondary
at Dravosburg, Pennsylvania, beginning October 22, 1990 and continuing
(System Docket MW-1766).
(2) As a consequence of the violation referred to in Part (1) above,
Claimants M. D. Spikerman, D. J. Eshenbaugh, D. T. Smith, J. B.
Spiering, J. B. Cypher, C. E. Chronick. M. V. Uhring, A. B. Roney, W. G.
Devlin, J. Bakos, R. C. Atkinson, W. J. Duffy, R. J. Spehar, L. E.
Kowalski, G. E. Little and L. E. Elizeus shall each be allowed eight (8)
hours' pay and two (2) hours' pay at their respective time and one-half
rates of pay for each day the outside forces performed said work."
FINDINGS:
The Third Division of the Adjustment Board, upon the whole record and all the
evidence, finds that:
The carrier or carriers and the employee or employees involved in this dispute
are respectively carrier and employee within the meaning of the Railway Labor Act as
approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the dispute involved
herein.
Parties to said dispute waived right of appearance at hearing thereon.
Form 1 Award No.31523
Page 2 Docket No. MW-30595
96-3-92-3-359
By letter dated August 24, 1990, the Carrier gave the Organization the following
notice:
"This is to advise that we intend to contract for the construction of 6,930
linear feet of precast concrete retaining wall along our Monongahela Line
(MP 20.0 to MP 22.7) Dravosburg, PA.
The project involves construction of two types of retaining wall structures
to replace failing Timber Crib retaining walls. The first type consists of
H-Piling augured in place with precast concrete lagging sections set
between the H-Piles. The second type consists of precast concrete wall
units installed by excavating the railroad embankment, installing the wail
units, then backfilling.
Construction of these retaining walls must be handled expeditiously
because our existing railroad embankment is failing and spilling onto the
adjacent PA State Route 837 creating a hazard to vehicular traffic and
poses a direct threat to the track structure.
Aside from the immediacy factor, Conrail does not have the necessary
auguring, lifting, excavating, compacting, paving and traffic control
equipment, nor do we possess the necessary expertise to perform this work.
We suggest we list this matter for discussion at our meeting scheduled for
August 30, 1990, at 10 a.m."
Conference between the parties on August 30, 1990 did not change the Carrier's
intention to contract out the work. By letter dated September 19, 1990, the Carrier
provided information requested by the Organization at the August 30, 1990 meeting.
Specifically, the Carrier provided information about cost of the contract (labor and
material); start and completion date of the project (September 17,1990 to be completed
by year's end); and information on traffic control. The Carrier also responded to the
Organization's other questions as follows:
"3. Q. What is different on this project in comparison to other types
of retaining walls installed by our employees?
Form 1 Award No.31523
Page 3 Docket No. MW-30595
96-3-92-3-359
A. This project involves the construction of two different types
of retaining walls, neither of which have been typically
installed by Conrail forces. They consists [sic] of H-pile and
concrete lagging type wall and a precast concrete 'L' shaped
type wall as opposed to a 'poured in place' type wall typically
constructed by Conrail forces. The construction is severely
complicated by the close proximity of the adjacent State
Highway and the need to drill and install H-pile sections, in
rock in some areas, beneath overhead Hi-Voltage power
lines which cannot be relocated due to the River, immediately
adjacent to the Highway.
4. Q. What is involved in the paving work
A. The project involves approximately 1600 SY of paving along
the State Highway shoulder adjacent to the Precast 'L' Wall
sections. This paving must be done in conjunction with
installation of the wall sections since the paving is considered
a structural component of the wall construction in these
areas."
Claim was filed on November 4, 1990 alleging that the Carrier violated the Scope
Rule of the Agreement "when it assigned outside forces to perform construction of
retaining wall starting October 22, 1990 ... and did not give the General Chairman
advanced written notice of its intention to contract said work."
We find that the Organization has not carried its burden in this case.
First, and clearly, notice was given by the Carrier to the Organization
of
the
Carrier's intent to contract out the work in question. The Carrier's August 24, 1990
notice detailed the retaining wall work contemplated by the Carrier. Contrary to the
Organization's argument, we find that the notice also sufficiently encompassed the
paving work associated with the project ("Conrail does not have the necessary .» paving
.» equipment »»") so as to put the Organization on notice that paving work was par
of
the project.
Indeed, the record shows that the Organization was fully aware
of
the Carrier's
intentions concerning paving work as part
of
the project. As shown by the Carrier's
September 19, 1990 letter, the Organization made specific inquiry at the August 30,
I
Form 1 Award No.31523
Page 4 Docket No. MW-30595
96-3-92-3-359
1990 conference concerning the paving work ("What is involved in the paving work?").
The Carrier's notice obligations have been met.
Second, the Organization argues that the retaining wall construction work
involved in the project was ordinarily and customarily performed by Carrier forces.
The Carrier effectively concedes that in the past its forces have constructed retaining
walls. In its September 19, 1990 response to the Organization's questions from the
August 30, 1990 meeting, the Carrier stated that "... retaining walls ... have been ...
installed by Conrail forces." Giving the Organization the benefit of the doubt that
Carrier forces have in the past constructed retaining walls, the record does not disclose
that the Carrier's forces have performed the type
of
work involved in this particular
project ("H-pile and concrete lagging type wall and a precast concrete 'L' shaped type
wall as opposed to a 'poured in place' type wall typically constructed by Conrail
forces"). As developed by the correspondence on the property, the record discloses only
one specific incident identified by the Organization ("Pictures
of
a wall constructed by
BMWE force at Manor, Pa in 1988"). That incident cited by the Organization is not
sufficient to refute the Carrier's assertions that the work in dispute was of a different
nature than that previously performed by the Carrier's forces.
Third, with respect to the Organization's allegations concerning the contracting
out of the paving work aspect of the project, again we find that the Organization has not
carried its burden. This aspect of the dispute was initially incidental to the retaining
wall work which was the original primary focus of the claim. However, the paving work
question remains. Again we find that as developed by this record the Organization has
not shown that the specific paving work in question was of the type ordinarily and
customarily performed by the Carrier's forces. See Third Division Award 30540 (where
the majority found that "[t]here is convincing evidence that the 'hot asphalt' work has
not been regularly performed by Carrier forces and is not contractually reserved to
them.").
Fourth, with respect to the Organization's arguments in this case relying upon
the Berge-Hopkins letter of December 11, 1981, see Awards 30515 and 30540, ('"Me
issue of whether the Berge-Hopkins [letter] is applicable has now been resolved in an
Award which is confined solely to this question. Public Law Board No. 1016, Award 66A,
this Carrier's property."). Those arguments made by the Organization are therefore
not persuasive.
Form 1 Award No.31523
Page 5 Docket No. MW-30595
96-3-92-3-359
Finally, this Board does not have jurisdiction to consider other arguments made
by the Organization in this case which are premised on matters outside
of
the terms
of
the Agreement.
Based on the record before us, the Organization has not carried its burden in this
case. The claim will be denied.
AWARD
Claim denied.
ORDER
This Board, after consideration
of
the dispute identified above, hereby orders that
an award favorable to the Claimant(s) not be made.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order
of
Third Division
Dated at Chicago, Illinois, this 25th day
of July
1996.
I