NATIONAL RAILROAD ADJUSTMENT BOARD
Form 1 THIRD DIVISION
Award No. 31525
Docket No. MW-30623
96-3-92-3-180

The Third Division consisted of the regular members and in addition Referee Edwin H. Benn when award was rendered.



PARTIES TO DISPUTE:

                  ( St. Paul and Pacific Railroad Company)


STATEMENT OF CLAIM:

      "(1) The alleged violation of the Agreement when the Carrier authorized and assigned Maintenance of Way work opportunities to an outside contractor (Railroad Salvage Associated of Milwaukee, WI) on March 29, 30, April 6, 7, 13, 14, 20, 21, 27, 28, May 4, 5, 11 and 12, 1991. (Carrier File: 8-00061, Organization File: C-12-91-C080-03)."


FINDINGS:

The Third Division of the Adjustment Board, upon the whole record and all the evidence, rinds that:


The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act as approved June 21, 1934.


This Division of the Adjustment Board has jurisdiction over the dispute involved herein.


      Parties to said dispute waived right of appearance at hearing thereon.


This dispute concerns the Organization's assertion that the Carrier contracted out the clean up of debris, wood and spoiled grain within the yard limits at Milwaukee, Wisconsin. As part of the arguments made by the Carrier, the Carrier asserts that it has similarly contracted out this work in the past without protest by the Organization.

Form 1 Award No. 31525
Page 2 Docket No. MW-30623
                                              96-3-92-3-180


      Third Division Award 30115 between the parties involved a similar dispute

concerning the : -iean up of spilled grain and track materials. The Board denied the
claim finding that "... this type of work has not by practice or tradition been customarily
performed by Maintenance of Way employees."

We do not find Award 30115 to be palpably in error. For purposes of stability, that Award must be followed. On the basis of that Award, this claim shall be denied.


                        AWARD


      Claim denied.


                        ORDER


This Board, after consideration of the dispute identified above, hereby orders that an award favorable to the Claimant(s) not be made.


                        NATIONAL RAILROAD ADJUSTMENT BOARD By Order of Third Division


                        Dated at Chicago, Illinois, this 25th day of July 1996.