Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 31591
Docket No. MW-30804
96-3-92-3-617
The Third Division consisted of the regular members and in addition Referee
Dana E. Eischen when award was rendered.
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Union Pacific Railroad Company (former
( Oklahoma, Kansas & Texas Railroad Company)
STATEMENT OF CLAIM:
"Claim of the System Committee of the Brotherhood that:
(1) Ile Agreement was violated when the Carrier assigned an outside
contractor (Woods Dirt Construction) to operate a backhoe tractor to tear
out and replace crossings between Medford and Pond Creek beginning
May 13 and continuing through July 3, 1991 (System File MW-91-40OKT/910578 OK-1).
(2) The Carrier also violated Article IV of the May 17, 1968 National
Agreement when it failed to furnish the General Chairman with a proper
advance written notice of its intent to contract out the work described in
Part (1) above and failed to afford a conference as contemplated by said
Agreement.
(3) As a consequence
of
the violations referred to in Parts (1) and/or (2)
above, Machine Operator C. F. Bill shall be compensated at the applicable
machine operator's rate
of
pay for an equal proportionate share
of
both
the straight time and overtime hours worked by the outside contractor's
forces in the performance of the work described in Part (1) above."
Form 1 Award No. 31591
Page 2 Docket No. MW-30804
96-3-92-3-617
FINDINGS:
The Third Division of the Adjustment Board upon the whole record and all the
evidence, finds that:
The carrier or carriers and the employee or employees involved in this dispute
are respectively carrier and employee within the meaning of the Railway Labor Act, as
approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the dispute involved
herein.
Parties to said dispute waived right to appearance at hearing thereon.
The record evidence in this case persuasively established that Carrier did,
in
fact,
provide the advance written notice required by Article IV of the May 17, 1981 National
Agreement, as augmented by the Berg-Hopkins Letter of December 11, 1981. The
Organization responded with a request for conference, which Carrier acknowledged and
placed on the agenda for the next regularly scheduled conference; or, alternatively, for
an earlier conference should the Organization desire. So far as the record shows, the
Organization took no further action to pursue the proffered conference and the matter
apparently never was conferenced. The same facts, issues and Parties were involved in
the partial denial of identical claims by this Board in Third Division Award 31015. The
same result is dictated by the record in this case.
AWARD
Claim denied.
ORDER
This Board, after consideration of the dispute identified above, hereby orders that
an award favorable to the Claimant(s) not be made.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Dated at Chicago,
Illinois,
this 29th day of August 1996.