Form i NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Award No. 31594
Docket No. MW-30811
96-3-92-3-611

The Third Division consisted of the regular members and in addition Referee Dana E. Eischen when award was rendered.

(Brotherhood of Maintenance of Way Employes PARTIES TO DISPUTE: (CSX Transportation, Inc. (former Atlanta and ( West Point Railroad Company)












FINDINGS:

The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds that:
Form 1 Award No. 31594
Page 2 Docket No. MW-30811
96-3-92-3-611

The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21, 1934.


This Division of the Adjustment Board has jurisdiction over the dispute involved herein.




On March 16, 1990, 13 of Carrier's coal cars derailed at MPYYG 87.0 on the Georgia Subdivision. The area alongside Carrier property, in which the derailment occurred, is privately owned pasture land. Carrier dragged the wrecked coal hoppers from the site, and placed them on the pasture land to be cut up.


After the cars were cut up and hauled away, an outside contractor (Elder & Sons) was called in and worked for 16 days cleaning up the derailment site. Carrier's use of the outside contractor to perform work which the Organization alleges it has historically performed, constitutes the gravamen of this dispute. Specifically, the contractor hauled mud and other debris and placed it back on CSX property.





Form 1 Award No. 31594
Page 3 Docket No. MW-30811


Carrier replied to the claim maintaining that the Organization's information was "inaccurate" and that the work which the contractor performed was "very sporadic" and completed by August 9, 1990. The Carrier further maintained that:




Further correspondence between the Parties did not bring about resolution to this issue. The dispute is now before the Board for adjudication.





At the outset, it is not disputed that Carrier failed to "meet and confer" with the General Chairman prior to entering into an agreement with the contractor. Therefore, Carrier clearly violated that portion of Rule 2 of the Agreement.


With regard to the work which the contractor performed on the private pasture land in question, Carrier argued that it did not possess the proper equipment to perform the necessary clean-up work. The Organization did not present any evidence which would lead us to question Carrier's assertion, therefore, that portion of the 1750 hours, some 342.5 hours, will not be considered further.

Form 1 Award No. 31594
Page 4 Docket No. MW-30811


However, we found the Organization's position persuasive with respect to the work which was performed along the drainage ditch, on Carrier's property. At the very least, Carrier should have conferred with the General Chairman prior to contracting out that portion of the work.


In that connection, the fact that Claimants were "fully employed" during the time that the drainage ditch repair was performed does not negate liability for the proven violation of Rule 2. Accordingly, Carrier is directed to compensate Claimants for 66 of the hours in dispute.


                        AWARD


      Claim sustained in accordance with the Findings.


                        ORDER


This Board, after consideration of the dispute identified above, hereby orders that an award favorable to the Claimant(s) be made. The Carrier is ordered to make the Award effective on or before 30 days following the postmark date the Award is transmitted to the parties.


                        NATIONAL RAILROAD ADJUSTMENT BOARD By Order of Third Division


                        Dated at Chicago, Illinois, this 29th day of August 1996.